M1A2 SEP v.4 / M1A2D: the main tank of the near future
In the United States, the process of development and modernization of the main combat tank M1 Abrams. In order to further improve performance and expand combat capabilities, a new project is being developed M1A2 SEP v.4 or M1A2D. The first machines of this type are planned to be manufactured and tested next year, and by the middle of the decade a full-scale restructuring of the existing equipment will begin.
Project by project
In 2015, General Dynamics Land Systems (GDLS) for the first time introduced an experimental tank of the M1A2 SEP v.3 version (System Enhancement Package ver. 3). Testing, fine-tuning and preparation of serial modernization for this project continued until 2017. At the same time, the Pentagon developed requirements for the next modernization project - SEP v.4 (since 2018, the M1A2D index has been used).
The development of this version of the Abrams was again entrusted to GDLS. The corresponding contract was signed in August 2017. According to its terms, in the coming years, the contractor had to prepare design documentation, and then build an experimental batch of tanks. The tests were supposed to start in 2020 or later, and in 2023 they were going to launch a serial modernization of equipment.
However, these plans failed to materialize. Due to the high requirements of the customer, the SEP v.4 project turned out to be quite complex in technical and organizational terms. In addition, the development was hampered by the pandemic, the global chip crisis and a number of other factors. As a result, the first stage of work has not yet been completed. GDLS continues to design and is not yet ready to transfer experimental equipment for testing.
According to the Pentagon, the construction and start of testing of the first M1A2D prototypes have been moved to 2023. Other stages of the project are shifting accordingly. Thus, the serial production of the updated equipment will be able to be established no earlier than 2025, and it will enter service only in the second half of the decade.
Production plan
In accordance with the existing contract in 2017, GDLS must develop a new project, and then prepare an experimental batch of seven tanks for testing. Such prototypes will be made on the basis of existing machines of previous modifications. Perhaps these will be tanks of the basic M1A2 version or vehicles that received one of the previous SEP packages.
Earlier it was reported that hundreds of tanks from combat units could undergo modernization under the M1A2D project. At the same time, more exact numbers or even their order were not called. In addition, it is not known what equipment will be upgraded. Both tanks with previous SEPs and older vehicles from storage that do not have such equipment can be upgraded.
It is possible that the Pentagon has not yet decided on such plans and is only working on them. A full production program can be developed only after the design of the SEP v.4 package is completed, when the technical and economic aspects of the project are finally determined.
However, it is already clear that the production of M1A2D tanks will be carried out in large quantities and will allow re-equipping a number of tank units and units. At the same time, a full transition to such a modification is simply impossible, and along with the M1A2 SEP v.4, tanks with the previous upgrade options will remain in service.
Recall that currently in the US units there are more than 1600 MBT versions of SEP v.2. The number of more advanced SEP v.3 / M1A2C has reached two hundred, and the release of such equipment continues. In total, more than 400 such tanks are going to be manufactured. It is likely that future production of the M1A2D will be on a comparable scale.
Package updates
The Pentagon and GDLS have already revealed some of the technical features of the M1A2 SEP v.4 project. Its purpose is to increase the operational and combat capabilities of the tank. Mobility should remain the same. Protection is going to be improved at the expense of additional funds and without changing the booking. Armament will be improved by replacing part of the instruments.
The new SEP v.4 update package includes all the major innovations and components of the previous one. In particular. overhead booking elements and the Trophy active protection complex are preserved. Also re-used auxiliary power unit, located in the engine compartment under the armor. The CROWS combat module also showed itself well, and will move to a new project, although its replacement with a newer product is not ruled out.
The protection of the M1A2D tank will be further improved with new means of optoelectronic countermeasures. The tank will receive a set of laser irradiation sensors, as well as a different set of smoke grenade launchers with the ability to shoot ammunition in different directions.
They do not plan to change the armament, but the fighting qualities will be increased due to improvements in the fire control system. It is planned to use new commander's and gunner's sights with high-definition color cameras and 3rd generation thermal imagers. In addition, a block of meteorological sensors will be replaced.
Like the existing M1A2C, the promising M1A2D tanks will receive the ADL programmable projectile control system. Thanks to this, they will be able to use the entire range of existing 120-mm unitary shots, incl. the newest M829A4 AKE and XM1147 AMP. The AKE product will significantly increase the potential of MBT in the fight against enemy armored vehicles. The AMP projectile, in turn, is a high-explosive fragmentation and is equipped with a programmable fuse with several modes of operation.
Benefits and Risks
All the details of the M1A2 SEP v.4 / M1A2D project are still unknown, but the available information adds up to a detailed picture. It allows you to determine the advantages and disadvantages of a new project and give it an overall assessment. More information should emerge in the future to refine the picture and update estimates.
In terms of the overall level of protection, the new M1A2D will to some extent surpass previous versions of the Abrams, including the latest production M1A2C. Ballistic protection will remain the same as SEP v.3. A similar KAZ will also be used. At the same time, the risks for the tank will be reduced due to new means of optical countermeasures, which will be able to hide it from enemy weapons and disrupt the attack.
As before, firepower is going to be increased simultaneously in several ways. Without affecting the main gun, they will update the SLA with the improvement of all its main parameters, as well as introduce new ammunition with increased performance and new functions. The self-defense tool in the form of CROWS DBMS will remain the same for the time being - with the same features and parameters. As a result, the fire capabilities of the tank will increase significantly, and it will be able to solve additional tasks.
Questions are raised by the mobility of the updated tank. In the course of recent upgrades, the combat weight of the M1 has constantly grown. In the M1A2C project, this parameter reached 66,8 tons. At the same time, a 1500 hp gas turbine engine. remained the same. Accordingly, there was a gradual deterioration in specific power, throughput and mobility. It is very likely that the promising M1A2D will become heavier again. Its mobility will again be reduced, and in addition, the possibilities for transportation will worsen.
Planned development
Thus, the Pentagon does not plan to abandon the M1 Abrams tanks and wants to get a new modification. It is planned to develop a service pack that affects a number of areas and is designed to positively affect key features and capabilities. This approach has been repeatedly used in the past and has shown its advantages - and therefore is being used again.
There are high hopes for the M1A2 SEP v.4 / M1A2D project. It will extend the life of the equipment, as well as improve its performance. However, the project has already encountered some difficulties and is behind the originally announced schedule. In addition, there may be some technical difficulties. Whether it will be possible to complete the work in accordance with the updated plans and give the army all the necessary equipment in a timely manner will become clear in the near future.
Information