The results of the Zelenodolsk plant them. A.M. Gorky in 2014 year
State defense order
Delivery of ships for the needs of the Russian Navy:
- under contract No. 3 / 1 / 1 / 0306 / GK-11-DGOZ from 29, April 2011 was built, tested and handed over to the Customer a small rocket ship of the 21631 project head. Number 633 "Great Ustyug." In 2014, the annual funding has been fully disbursed.
- under contract З / 1 / 1 / 0086 / ГК-13-DGOZ from 04, March 2013 was built, passed tests and handed over to the Customer an anti-sabotage boat of the project 21980 head. No. 986. In 2014, the annual funding has been fully disbursed.
- under contract З / 1 / 1 / 0086 / ГК-13-DGOZ from 04, March 2013 was built, passed tests and handed over to the Customer an anti-sabotage boat of the project 21980 head. No. 987. In 2014, the annual funding has been fully disbursed.
Construction of ships for the needs of the Russian Navy:
21631 small rocket ships
- under contract No. 3 / 1 / 1 / 0667 / GK-12-DGOZ from 19 in October 2012, the construction of small rocket ships of the project 21631 was conducted. No. 634 "Green Dol", head. № 635 "Serpukhov". As of December 31 2014 g:
- by request head. No. 634 main equipment is loaded and assembled. In accordance with the construction schedule, the electrical installation of the equipment is completed, the construction certificates are closed. Work was underway to prepare for the launch of the water order.
- by request head. No. 635 main equipment is loaded and assembled. In accordance with the construction schedule, the electrical installation of the equipment is completed, the construction certificates are closed. Work was underway to prepare for the launch of the water order.
In 2014, the annual funding has been fully disbursed. The deadline for orders head. №№ 634, 635 - 2015 year.
- under contract No. З / 1 / 1 / 0005 / GK-14-DGOZ from 25 December 2013. construction of small rocket ships of the project 21631 is in progress. №№ 636, 637, 638, 639. Currently:
- by request head. No. 636 contracts for the supply of basic equipment have been concluded and approved. In accordance with the construction schedule, a hull is being formed. Installation of foundations and welded saturation is in progress. The assembly of the 6 unit is in progress. Began to test the ventilation ducts and fresh water tanks.
- by request head. No. 637 contracts for the supply of basic equipment have been concluded and approved. In accordance with the construction schedule, cutting of metal, production of hull sections is underway. Began to the formation of the body, the manufacture of welded saturation.
- by request head. No. 638 is the conclusion and advance payment of equipment supply contracts. In accordance with the construction schedule, cutting of metal, production of hull sections is underway.
- by request head. № 639 is the conclusion of contracts for the supply of equipment. In accordance with the decision of the Deputy Minister of Defense of the Russian Federation Borisov Yu.I. and the construction schedule bookmark housing order will be held 10 April 2015 of the year.
In 2014, the annual funding has been fully disbursed. Delivery time: head. No. 636 - 2017 year, head. №№ 637, 638 - 2018 year, head. No. 639 - 2019 year.
22160 project patrol ships
- under contract No. З / 1 / 1 / 0193 / GK-14-DGOZ from 11 on April 2014. The construction of the head patrol ship of the project 22160 is in progress. No. 161. At present, the conclusion and advance payment of equipment supply contracts. In accordance with the construction schedule today, the 3 block on the stocks has been formed. Production of the 2 block, cutting of metal for the manufacture of sections of the 4 block. In 2014, the annual funding has been fully disbursed. The deadline for the order is 2017 year.
- under the contract З / 1 / 1 / 0556 / GK-14-DGOZ from October 09 2014. The construction of the patrol ships of the project 22160 head. No. 162, 163, 164, 165, 166. Currently:
- by request head. No. 162 is the conclusion and advance payment of equipment supply contracts. In accordance with the construction schedule, the production of the bottom sections of the 3 block has been completed, metal is being cut for the manufacture of sections of the 2 block.
- on orders head. №№ 163, 164, 165, 166 is the conclusion of contracts for the supply of equipment. In 2014, the annual funding has been fully disbursed. Delivery time: head. №№ 162, 163, 164 - 2018 year, head. №№ 265, 166 - 2019 year.
21980 anti-diversion boats
- under contract No. З / 1 / 1 / 0494 / GK-14-DGOZ from September 02 2014. construction of anti-diversion boats of the project 21980 is in progress No. 988, 989, 990. Currently:
- by request head. № 988 - the conclusion of contracts for the supply of equipment, the body of the order is formed, the installation of welded saturation.
- on orders. Head №№ 989, 990 is working on the conclusion of contracts for the supply of equipment.
In 2014, the annual funding has been fully disbursed. Delivery time: head. No. 988 - 2017 year, head. №№ 989, 990 - 2018 year.
22570 Project Floating Dock
- under the contract / 1 / 2 / 0144 / GK-12-DGOZ from 18 in May 2012, the construction of a transport floating dock of the project 22570 heading. No. 571. Currently the order is floated. The equipment is being installed and wired. In 2014, the annual funding has been fully disbursed. The deadline for the order is 2015 year.
It is noteworthy that in the reporting there is no information about the construction of new 15310 “Volga” and “Vyatka” cable vessels for the Russian Navy, the solemn ceremony of which was held on January 6 2015.
Construction of ships for the needs of the Coast Guard of the Federal Security Service of Russia:
- under contract No. 6-2011 from 26.12.2011. The construction of the border guard ship of the project 22100 is in progress. No. 111. Currently, all the equipment is loaded, the order is floated, completion work is underway, mooring tests. In 2014, the annual funding has been fully disbursed. The deadline for the order is 2015 year.
Addition on the fate of the order for two more PSCR “Ocean”: despite the sanctions against MTU diesel engines that were supposed to be put on these ships, their construction plans remain, according to an updated version of the FSB procurement schedule in April, the next two state contracts should be signed (head. 112-113). The deadline has moved from 2018 to 19 year, the price has increased from 7,8 billion to 8 663 772 640 rub. for one ship.
Building ships through military-technical cooperation
Execution of the State Contract for the supply of frigates "Cheetah-3.9" to the Socialist Republic of Vietnam
In 2014, in accordance with the Government Contract for the supply of frigates "Cheetah-3.9", the presentation of three phases of construction was provided for in SRV. In the second decade of February 2014, during the visit of the delegation of the Ministry of National Defense of the Socialist Republic of Vietnam, an act of acceptance of the first stage of construction of the order number 957 was signed. In August 2014, the plant presented work to the Customer 704, performed in the volume of the second stage of construction of the order No. 956 “Formation of the hull on the stocks”. In December, the 704 customer was presented work performed in the volume of the second construction stage of the order head number 957.
Supply of ZIP-B kit for frigate “Cheetah-3.9”, serial number 954
In February, 2014, the plant delivered a set of spare parts and tools to NRW. In May, 2014, the Customer 704, carried out in Vietnam the acceptance of the ZIP-B kit.
Prospective supplies of small rocket ships of the 21632 Tornado project to the Republic of Kazakhstan
Since September, 2014 has been working with the Rosoboronexport OJSC to prepare and sign contract documents for the supply of small rocket ships of the 21632 Tornado project to the Republic of Kazakhstan. In December, 2014 prepared a draft contract and the delegation of the Russian side visited the Republic of Kazakhstan to agree on the main articles of the contract document. As of February 2015, the Kazakh side has not finally decided to supply the Tornado MRC.
Prospective shipments of the patrol ship based on the project "Cheetah-3.9" to Sri Lanka
In November, 2014, together with Rosoboronexport OJSC, prepared a commercial offer for Sri Lanka for the supply of a patrol ship based on the project “Cheetah-3.9”. In January, a commercial proposal was submitted to 2015 by the Sri Lanka Military Attache for further approval.
Civil shipbuilding market
In 2014, the factory:
- the construction of two passenger ships of the project A217-1, factory building No. 231 and 232 was completed;
- construction of two high-speed passenger motor ships of the A145-1 project has been launched;
- the construction of a series of 4 units of non-propelled dry-cargo barges of project No. 3136 was started;
- construction of the DF5000 project dredger has been launched.