The Ministry of Defense has accumulated claims to Spetsstroy
According to the source, the contract from 2012 was disrupted for a comprehensive arrangement of the military town on the island of Iturup. “The contractor should complete everything by November next year's 15. To build dormitories for officers and soldiers, a checkpoint, a division headquarters, a training building for 330 people, a first-aid post for 50 beds, a nutrition center, a parade ground, training grounds, fuel storage, warehouses, a sports training complex and other facilities, ”said the source.
In total, Spetsstroy should hand over 150 facilities located in the Far East, including the Kuril Islands, next year. The cost of the project 12 billion rubles. The military expected to get modern autonomous small towns with developed infrastructure on the islands, but the builders could not organize work either on Iturup or Kunashir.
“The general contractors of FSUE“ Spetsstroyinzhiniring ”, GUIR No. 2 (organizations under the jurisdiction of Spetsstroy) started construction only in July of this year,” a newspaper source told the Ministry of Defense. “At the same time, more than 3 billion rubles were advanced in accordance with the contract. Organizations that performed the work did not see these funds. ”
According to the source, “in fact, there is no design estimate for which the general contractor is responsible, neither the working documentation for the facilities, nor the technical conditions of the work, and of the required 700 people today less than a third are hired.” “The delay in performing design and survey work on 10 in November was 469 days,” said the source. - For the Kuril Islands, this is equivalent to a delay of several years. In their defense, contractors merely argue that they could not begin construction "due to weather conditions."
The same sad picture and Kunashir. “Under the contract of 2012, Spetsstroy’s contractors — Spetsstroyinzhiniring and GUIR No. 2 — had to hand over similar infrastructure to the base by 2015, but so far they could only deploy a temporary administrative town to 20 people and bring building materials. Only 32 people work on the island, while at least 600 specialists are required, ”a source said.
The newspaper reminds that not so long ago the head of the FSUE “GUSS“ Dalspetsstroy ”(submits to Spetsstroy), retired lieutenant-general Yuri Khrrizman, who for two years stole (squandered) 1,8 billion, was arrested.
According to the plans of the Ministry of Defense in the Kuril Islands, the rearmament of the 18th division of missile forces and artillery, which includes the 484th machine gun and artillery regiment on Iturup and the 46th on Kunashir, should be completed. Only 3,5 thousand military personnel. 80% of the regiment’s equipment is in need of repair or must be discarded. Units are still armed dug in the ground. tanks T-34 and IS-2/3.
“In order to guarantee Russian sovereignty over the Kuril Islands,” told the newspaper National Defense magazine Igor Korotchenko, “in addition to the planned rearmament of the 18 division stationed there, it is necessary to deploy two C-400 Triumph anti-aircraft missile systems, which There will be anti-aircraft missile-gun systems "Pantsir-С1". As well as the coastal missile system "Bastion" with anti-ship missiles "Yakhont" and several modern radar control airspace to ensure a solid radar field. "
In addition, according to the expert, after the reconstruction of the airfields in the Kuril Islands, an air base can be created, equipped with new Su-35.
“It can be assumed that the case will not be limited to lawsuits for the recovery of penalties in the Kuril Islands. Disruption of work here directly affects the plans of military construction and national security, ”the publication sums up.