Nuclear "Arktika"

Arktika, the lead icebreaker of the new series, 2020
Currently, the Russian industry is implementing a large and important project to upgrade the nuclear icebreaker fleetConstruction is underway on new Project 22220 Arktika icebreakers, which will replace obsolete and outdated vessels. Four new icebreakers have already been built and commissioned. The next pennant is scheduled to begin trials in 2026, and its delivery to the customer is scheduled for the end of the year.
First successes
The decision to develop and build a new series of nuclear-powered icebreakers for FSUE Atomflot was made in the 2000s, taking into account the state of the existing fleet. Development of the new project, codenamed "Arktika" and numbered "22220," was entrusted to the Iceberg Central Design Bureau (St. Petersburg). The nuclear power plant was designed by the I.I. Afrikantov Design Bureau (Nizhny Novgorod). Numerous other organizations were also involved in the design and construction.
On August 23, 2012, Atomflot, part of the state corporation Rosatom, and the Baltic Shipyard (St. Petersburg) signed a contract for the construction of the lead icebreaker of the new Project 22220. The contract value reached almost 37 billion rubles. According to initial plans, the vessel, named "Arktika," was to be delivered to the customer by the end of 2017.

Sibir and Arktika under construction, 2018
The icebreaker's keel was laid on November 5, 2013. Construction on the slipway took nearly three years, and the Arktika was launched in June 2016. However, the work overall was delayed. In mid-2017, Rosatom management reported that the construction had encountered several problems. Not all companies involved in the project were up to the task, leading to delays. Furthermore, in early 2020, one of the propulsion motors failed, hampering further work.
However, all obstacles were successfully overcome. The Arktika's acceptance certificate was signed on October 21, 2020. By the end of that year, the icebreaker began operations on the Northern Sea Route. It complemented the existing vessels of its class and improved the icebreaker fleet's overall capabilities for escorting merchant vessels.
Icebreakers in series
At the end of May 2014, a second contract for the construction of new icebreakers was awarded. This time, the Baltic Shipyard was commissioned to build two vessels at a total cost of 84,4 billion rubles. The icebreakers were scheduled to enter service in the early 2020s.
The keel of the first production icebreaker was laid in May 2015; the vessel was named "Sibir." The first phase of construction took just over two years, and the icebreaker was launched in September 2017. At that time, its delivery was scheduled for mid-2020. However, unforeseen difficulties arose again, forcing a revision of the work schedule. Ultimately, Atomflot accepted the new vessel at the end of 2021.

Icebreaker Ural, November 2022
In July 2016, the third icebreaker in the series, the Ural, was laid down. In May 2019, the Baltic Shipyard launched the vessel and transported it to the outfitting quay. Fitting out and testing were expected to take approximately two years, but they too were delayed. The acceptance certificate was signed in November 2022.
In August 2019, another contract for new icebreakers was awarded. Atomflot ordered two Pennants for a total of 100 billion rubles. Construction preparations began shortly thereafter.
In accordance with the new contract, the icebreaker Yakutia was laid down in May 2020. By this time, all the technologies and manufacturing nuances had been perfected, allowing construction on the slipway to take only two and a half years. The icebreaker was launched in November 2022. Then, approximately two years were spent on completion, testing, and other procedures. In accordance with the original schedule, Yakutia was delivered to Atomflot in December 2024.
Continuation of construction
At the launch of Project 22220, it was planned to build five new icebreakers to replace the existing pennants. However, later, after construction of the first icebreakers had begun, it was decided to expand the series to seven units. This number of vessels will not only maintain but also improve the capabilities and potential of the icebreaker fleet.

Installation of a nuclear reactor in the hull of the future vessel Yakutia, August 2022.
In accordance with these plans, construction of three new icebreakers is currently underway. Work is at various stages and progressing well. Results are expected in the coming years.
Thus, the fifth icebreaker in the series, Chukotka, was laid down in December 2020. Like Yakutia, it is being built in accordance with a 2019 order. It was launched in early November 2024. According to available information, fitting-out afloat is currently being completed, and the vessel will begin sea trials in the coming months. It is scheduled to be delivered to the customer at the end of this year.
In 2021, the construction of two more icebreakers was announced. A corresponding contract was awarded shortly thereafter. Due to a number of significant factors, the total cost of these vessels reached almost 118 billion rubles, with 58,9 billion allocated by the state.
In January 2024, the keel-laying ceremony for the sixth icebreaker was held at the Baltic Shipyard. This vessel, named "Leningrad," is currently on the slipway. Launching and completion are scheduled for 2026. Subsequent work will take approximately two years, and the customer will receive the vessel by the end of 2028.

Arktika at the North Pole, October 2020
Finally, on November 18, 2025, construction of the icebreaker "Stalingrad" began. It is scheduled to be launched in 2028. Delivery to the customer is expected by the end of 2030. This will likely complete the Arktika series of icebreakers.
Obvious progress
Thus, to date, the domestic industry has built and delivered four new-type icebreakers to the customer, is preparing a fifth for trials, and is building two more. Almost 13 years have passed since construction began on the new series of vessels, and its completion will require approximately four more years.
Following the current construction, the existing nuclear icebreaker fleet will be completely renewed. According to current plans, the older icebreakers will remain in service until the mid-1930s. By that time, Atomflot will receive all the ordered pennants for the new Project 22220 and fully commission them.
This fleet renewal has several obvious positive consequences. First and foremost, these are related to the new technology. Modernly built vessels boast improved technical, operational, and service characteristics. They are easier to operate than their predecessors and also offer other advantages relevant to real-world applications.
Furthermore, the Arktika-class icebreakers are new. They haven't yet exhausted their service life, allowing them to remain in service for decades to come. The issue of equipment obsolescence, which arose in the past, will no longer be relevant for a long time.
It's worth noting that Russian industry is successfully building highly complex nuclear-powered vessels and overcoming all challenges. Unfortunately, the first orders fell behind schedule due to a lack of experience and foreign sanctions. However, these challenges were subsequently overcome, and new icebreakers are now being built and delivered to customers on schedule.
Given the work and achievements of recent years, there is now no doubt that the Baltic Shipyard and its associated companies will complete construction of the planned series of icebreakers. Furthermore, it is expected that the remaining vessels will be delivered to Atomflot on schedule and without delays or other problems.
Information