Chernobyl Nuclear Power Plant Unit 4 Before the Explosion: The Last Fatal Steps, or Why No One Wanted to Say "Stop"

11 493 71
Chernobyl Nuclear Power Plant Unit 4 Before the Explosion: The Last Fatal Steps, or Why No One Wanted to Say "Stop"

Let's briefly recap what happened before the tragedy. The personnel fell behind schedule for vibration testing before the scheduled maintenance. It became known (according to Dyatlov's testimony) that the TG-8 vibration test on April 25, 1986, was not conducted, first due to the TG-8 itself being unprepared, and then due to the dispatcher's prohibition on transferring the load to TG-7. Consequently, the vibration test had to be combined with a coastdown, which fatally increased the risk of an accident.

Then, the Kyivenergo dispatcher's ban on April 25, 1986, disrupted the vibration testing schedule and the experiment itself, which also tragically affected the entire chain of events.



There is an extremely important (though not proven) hypothesis already considered about the possibility of xenon poisoning of the reactor, created as a result of both the planned reduction of power by 50% on the eve of the experiment and the subsequent delay in its reduction due to the ban by KyivEnergo.

A. Dyatlov then ordered the reactor power to be reduced to 200 MW, despite this being inconsistent with the test program. This was a fateful step, which largely predetermined the possibility of an accident. This power level was an intermediate level, poorly studied, and at this level, the reactor behaved unpredictably (a fact the Chernobyl Nuclear Power Plant management was aware of). At low reactor power, the water temperature became close to the saturation (boiling) temperature, yet the technical documentation did not specifically prohibit operation at this power, although its plot suggested this.

As our leading nuclear power plant safety specialist, V. Asmolov, noted:

It stabilized at 200 megawatts. That's less than 10 percent... For us in the project, this was an unexplored power level. Because a reactor operates at this power level either when it's starting up or when it's shutting down.

According to Fomin's testimony in court:
I believe the violations of program provisions are the main cause of the accident. First and foremost, the reduction of the reactor's power to 200 MW.

Prosecutor: Who, in your opinion, is the main culprit of the accident?

Fomin: Dyatlov, Akimov, who allowed deviations from the program.

Perhaps 200 MW was needed to legally disable the reactor shutdown protection system (bypassing the requirements of the main Regulations governing the operation of this protection) by shutting down the reactor shutoff valves of both turbines in accordance with the "Regulations for Switching Keys and Cover Plates...," which, according to this document, is disabled at power levels below 100 MW electrical. However, this document, to which Dyatlov refers, is not publicly available.

Perhaps, as V. Dmitriev previously indicated, the personnel believed that 760 MW(t) for conducting vibration tests of the turbine generator was too much, so they reduced it to 200, and Metlenko also said in court that he needed 35–45 MW(el), i.e. 200 MW(t).

INSAG-1 believes that Dyatlov also needed to turn off the protection so that he could repeat the experiment (in case of failure), although competent experts, including those who advised the author, acknowledged that under these conditions, repeating it would have been absolutely impossible.

Finally, there's a hypothesis that the power reduction was necessary to conduct vibration testing. This possibility is also discussed by the author of the textbook, V. L. Gurachevsky (Introduction to Nuclear Energy, Rosatom Library):

Combining the coastdown and vibration tests had two catastrophic consequences: a power reduction, which increased the risk of reactor shutdown; and the shutdown of the reactor protection system, which shut down both turbine generators, which, as we will see below, was also a contributing factor to the accident. This was done so that the turbine could continue to idle during the tests without being shut down by the protection system. Disabling this protection system, an important safety measure, led to a loss of reactor control and, ultimately, an explosion. The two programs are incompatible and contradictory. If not for the vibration tests, the accident could have been avoided and the coastdown could have been carried out using the old scheme, without disabling the protection system for both turbine generators.

Following errors by the SIUR in reactor control, or as a result of xenon poisoning, or a power reduction for vibration testing, the reactor shuts down. The moment the reactor shut down actually became a turning point. Fate offered a real chance to avoid the accident—if the personnel had shut down the reactor, the accident would not have occurred!

However, according to Komarov, an official from a department (or sector) of the Central Committee of the CPSU may have given instructions to A. Dyatlov to increase the power and to conduct the experiment, threatening him with retirement.

Dyatlov then orders a power increase, which was established during the judicial investigation, although he denies it. The reactor begins to be raised from the pit—this was done quite quickly, from 12:38 AM to 12:42 AM—within four minutes, the power was raised to 160 MW, and a little later, by 1:03 AM, to the planned 200 MW. Conducting the experiment at this power level was a gross violation of the test program, which called for a coastdown of 700 MW.

Most importantly, the increase in power to 200 MW due to xenon poisoning of the reactor was achieved by removing the maximum possible number of control rods, while their number in the core became unacceptably low, a gross violation of the Regulations. The reactor was poisoned, and its condition was uneven. And this was a fatal error on the part of the personnel. However, there are a number of caveats to this, discussed below.

We would like to emphasize that the assumptions and conclusions we have made are not adequately reflected in any official document regarding the investigation into the causes of the accident, which must continue – all documents are kept in secret archives in Moscow.

The staff then moves on to preparing for the coastdown tests, taking the final, fateful steps.

Disabling protection for blocking both TGs (for closing the SRV of both turbines) and more


During the tests in 1982–85, steam stopped flowing to the turbine (to ensure pure inertia of the turbine, steam access was closed through valves—stop and control valves (SRVs)), but at the same time, the reactor, according to the experimental design, was automatically shut down (!) by special protection for closing the SRVs of both turbines.

In contrast, the 1986 tests were conducted with this protection disabled, ostensibly because the personnel intended to repeat the experiments in the event of failure. According to the report (No. 1 INSAG-1):

The existing A3 for shutting down the recovery valves of two turbogenerators (Turbine Generator No. 7 was shut down on the afternoon of April 25, 1986) was blocked to allow for a repeat test if the first attempt was unsuccessful. This constituted yet another deviation from the test program…

According to the NIKIET report:

Since it was not planned to shut down the reactor, in order to ensure that automatic protection systems did not interfere with the testing, the formation of the AZ-5 mode for emergency exceeding the specified power in a small range (AZMM) was disabled, the formation of the AZ-5 mode for emergency increase in the rate of power increase in the starting range (AZSP) was disabled, a blocking was introduced for the formation of an emergency signal for disconnecting one of the turbogenerators, the LAR system, designed for automatic regulation of power in the energy range, was disabled - instead, the backup automatic power regulation system of the reactor, including AR1 with automatic overcompensation of its rods by moving the ZAR-AR rods, was turned on, protection for a decrease in the water level in the BS was not introduced.

As Academician A. Alexandrov aptly noted: "The only thing missing [at the unit] was protection against a fool who might decide to disable the protection for his own experiment." The regulations prohibited overriding protections other than those described in the control procedures. The main criticism that can realistically be leveled at the reactor designers is that such a possibility existed.

Why they didn't activate the safety system later remains unclear. Perhaps they didn't consider it important. Dyatlov (according to him) mentioned shutting down the reactor at the beginning of the experiment during the briefing; this cannot be verified, as there were no witnesses. Failure to shut down the reactor was a fatal mistake, and why Dyatlov left the reactor running at full power is now a matter of conjecture.

It is also suggested that the theory about the shutdown of both transmission lines is an excuse used by A. Dyatlov to justify his mistake: in reality, the personnel would not have been able to repeat the experiment. This hypothesis was put forward by specialists who advised the author during the writing of this article.

The tests themselves involved shutting down some equipment (turbine, main circulation pump, and fuel pump), which would otherwise have had to be restarted. This is a lengthy process, especially with modified electrical circuits. The test program made no mention of repeat tests.

Another possibility is that the staff allegedly "forgot" to turn it on. Here's what V. Zhiltsov, a participant in the accident investigation, had to say about this:

To conduct vibration tests on the turbogenerator, they removed one of the safety switches, and after completing the tests, they forgot to re-enable it... The reactor was supposed to shut down automatically upon the "two turbines shut down" signal. But one turbine was already running, and the eighth turbine, where the ill-fated "coastdown" test was being performed, had its safety switch locked because they "forgot" to unlock it after the vibration tests were completed. This was a serious fault on the part of the personnel. Therefore, the reactor continued to operate for almost 30 seconds after the turbine was disconnected, after which an attempt was made to shut it down using the AZ-5 button. According to the entry in the SIUR Operational Log, this was done by L. Toptunov. A few seconds later, he also turned the "clutch power off" key.

These 30 seconds were enough for the reactor to run away. If this is indeed the case, then the official explanation for the personnel's actions regarding the shutdown of the protection systems may not reflect their actual logic.

Perhaps the unit's personnel didn't fully appreciate the risks of shutting down the recovery valve on the remaining turbine, even though their more experienced peers should have understood. Perhaps they assumed that, with the reactor operating at 200 MW, the pressure increase would be slow. Steam could be discharged into the condensers via the BRU-K bleeder (for excess steam when pressure rises).

The main steam drain in an operating reactor is through the turbine. If the turbine is shut down, the drain is shut off, but the reactor continues to generate steam, leading to a pressure increase. This protection was created to prevent a pressure surge in the primary circuit associated with a turbine shutdown, which stops consuming steam.

As a result, the blocking of protection to block both turbogenerators under specific conditions of the accident development (see below – a sharp decrease in feedwater consumption, a slowdown in operation and a breakdown of the main circulating pump) was one of the key factors in the development of the accident.

As stated in the court ruling: “Fomin, Dyatlov, Kovalenko… did not regulate the removal of excess steam from the circuit.”

Dyatlov at the trial:

It was stated that the AZ-5 shutdown should not have been initiated after two turbine generators were shut down. However, this was done in accordance with the operating procedures and did not affect the progression of the accident. At power levels below 100 MW (electrical), this protection should be disabled. Therefore, there was no violation of the operating procedures.

Both the State Panic Administration and INSAG-7 do not consider the shutdown of this protection following A. Dyatlov to be a violation for formal reasons, which seems very strange.

However, as a member of the IXBT forum believes, this "...is true for the TG load shedding protection, and only at the moment it's activated. The AZ-5 protection for TG shutdown (failure of two of the four SC) is activated immediately after connection to the grid and is deactivated only when the reactor is shut down. This was the case before 1986, and it remains the case today."

In fact, according to the Regulations, this protection is activated immediately after the TG is connected to the grid and deactivated only after the TG is disconnected. This means that disabling this protection during the entire period the power unit is operating with an electrical load is prohibited. However, Dyatlov cites a certain Regulation on Switching Keys and Cover Plates, which is absent from the documents, or is attempting to justify his error.

At the same time, Nikolai Fomin, the chief engineer of the Chernobyl Nuclear Power Plant, who was responsible for safety at the Chernobyl Nuclear Power Plant and who became the main "conductor" of the notorious "experiment," openly admits that the disabling of this protection was the most important cause of the accident:

Prosecutor: In your opinion, what could have prevented the accident?
Fomin: If the AZ-5 shutdown from the shut-down valve hadn't occurred, the unit would have remained intact... In 1982, '84, and '85, during the program, the AZ-5 signal to the reactor was sent by shutting down the shut-down valve on the turbine. And in 1986, changes were made to this aspect. Now it's clear to me that the program should have been coordinated with specialists. There was no point in keeping the unit running at power if all the turbine generators were at a standstill.
According to Yu. A. Potemkin, former deputy head of the GVP (Main Military Prosecutor's Office) of the USSR: "...they shut down both turbines while the reactor was still running. This is madness, frankly speaking. This led to the explosion."
From Metlenko's testimony:
"Prosecutor: Was it necessary to shut down AZ-5 when 2 TGs stopped?
Metlenko: "No, absolutely not. We said that with our program, the reactor needs to be shut down."

SIXTH TRAGIC ERROR (FATAL) – DISABLING THE PROTECTION TO BLOCK BOTH TGs.

Connecting additional main circulation pumps


Technical news feed:

From 00h 43mm 35s to 44m 40s — signal “1PK up”.
From 00:43:36 to 51:23 — signal of malfunction of the measuring part of the AR-2.
00h 43m 37s — protections for increasing the condensate level in the SPP compressor station and for increasing the level in the evaporator are activated.
/The protection data was also removed in violation of the test program in order to prevent the reactor from being shut down/
From 00:43:37 to 51:45 — emergency level deviations in the base station.
From 00:49:19 to 51:23 — signal “1PC down”.
00h 51m 23s — activation of BRU-K1 TG-8.
00h 52m 27s — emergency deviations of the LEVEL in the BS.
01h 00m 02s — signal of malfunction of the measuring part of AR-2.
01h 00m 04s — emergency level deviations in the left half of the BS.

Between 12:43 a.m. and 1:00 a.m., personnel received at least four emergency signals. In forum discussions, several participants wrote that nothing alarming occurred. According to Dmitriev, the reactor was operating unstably, as there were alarms for water level deviations in the reactor compartment and the activation of the BRUK-K (excess steam pressure).

01 h 02 min 20 s — increase in feedwater flow rate from 104 to 424 t/h on the left half to increase the water level in the BS.

To stabilize the water level in the boiler system and reduce the pressure in the circuit by cooling the circuit water, the staff sharply (almost fourfold) increases the feedwater flow rate in the circuit. The feedwater regulator was turned off.

01h 03m — N(T) = 200 MW. Disconnection of TG-8 from the grid, measurement of vibration XX with the generator disconnected.
01h 04m - MCP-12 is turned on.
01h 06m 02s — emergency level deviations in the left half of the BS:
increasing the feed water flow rate from 192 to 1170 t/h (left) to raise the water level in the BS.
01h 07m - MCP-22 is turned on.
01h 09m — water flow rate reduced to 100 t/h on the left and right.
01h 09m 45s — emergency level deviations in the BS.

As part of the test program, additional main circulation pumps (MCPs) 12 and 22 were activated to provide additional reactor cooling in the event of a slowdown in the main circulation pumps. The reactor began to operate erratically, and the water level in the separator drums dropped to the emergency level. To prevent a reactor shutdown, personnel disabled several safety devices.

According to G. Medvedev,

…the total water flow through the reactor increased to 60 cubic meters per hour, compared to the standard of 45… per hour, which is a serious violation of operating regulations. Under these operating conditions, pumps can disrupt flow, and vibrations in the circuit pipelines can occur due to cavitation (boiling of water with strong hydraulic shocks). The sharp increase in water flow through the reactor led to a decrease in steam generation, a drop in steam pressure in the separator drums where the steam-water mixture from the reactor is fed, and undesirable changes in other parameters.

According to INSAG-1 Report for the IAEA:

Operators attempted to manually maintain the reactor's key parameters—steam pressure and water level in the steam separator—but were unable to do so fully. During this period, steam pressure drops of 0,5–0,6 MPa and water levels below the emergency setpoint were observed in the steam separator. To prevent a reactor shutdown under these conditions, personnel blocked the emergency control signals for these parameters.

According to the report of the State Nuclear Academy of Sciences (1991), the increase in consumption was a violation of the Regulations: “Increase in consumption for individual main circulation pumps to 7500 m3/h (violation of clause 5.8 of the TR).”

Let's see how reactor designer Nikolai Dollezhal described this situation:

...Of the four pumps, two were fed by the auxiliary busbars, meaning they had normal voltage and frequency. Two were fed by the busbars of the generator being tested, with a steadily declining speed and, consequently, a declining frequency, which affected their performance characteristics—i.e., speed, flow rate, and developed pressure. A situation arose in which four pumps with different, constantly changing characteristics were operating simultaneously. Operation of such a system can be accompanied by the most unexpected manifestations. It should also be noted that the generator being tested was not in freewheel mode at all, as it was loaded, albeit slightly, by the motors of the four main circulation pumps: this slowed it down and forced it to reduce speed...

To stabilize the water level in the reactor coolant system and the pressure in the circuit by cooling the circuit water, the crew sharply (almost quadrupled) increased the feedwater flow rate in the circuit. After 30 seconds, the operator managed to maintain the level, increasing the feedwater flow rate more than threefold. However, as soon as the cold water from the reactor coolant system reached the core, steam generation significantly decreased, causing a decrease in the volumetric steam quality. This caused the automatic control rods to move upward, and the automatic control system began withdrawing the rods from the core (01:19:39 – signal "1 PK up", reactor power is falling), reducing the ORM.

The combination of two factors: reactor poisoning and increased feedwater consumption, led to the fact that at 1:22:30 a.m., according to the PRIZMA printout, there were only 6–8 rods in the active zone, calculated as fully immersed.

The reduction in steam generation led to a slight pressure drop in the BS. About a minute later, the high-speed pressure-reducing device (BRU-K), through which excess steam was vented into the condenser, closed. This contributed to a slight reduction in the rate of pressure drop. However, the pressure continued to decline slowly until the start of the tests. During this period, it dropped by 5 kgf/cm².

The general characteristics of the neutron field at that moment in time are as follows: in the radial-azimuthal direction it is practically convex, and in height, on average, it is “double-humped” – with a higher energy release in the upper part of the active zone.

This field distribution was a consequence of the reactor's current state: a burned-out core, almost all control rods at the top, a significantly higher steam quality in the upper part of the core than at the bottom, and greater 135Xe poisoning in the central parts of the reactor than in the peripheral parts. Operating the reactor at 200 MW(th) resulted in a large accumulation of 135Xe, which would not have occurred at a reactor power of 700-1000 MW(th).

THE SEVENTH TRAGIC ERROR IS CONNECTING ADDITIONAL RCPs AND BLOCKING THE PROTECTION DEVICE BY SIGNALS OF INSUFFICIENT WATER LEVEL AND STEAM PRESSURE.

A sharp decrease in feedwater consumption


When, in the opinion of the operator, the reactor parameters returned to normal, he sharply reduced the feedwater flow rate, practically to zero, which turned out to be a fatal step, since it led to an increase in the coolant temperature at the reactor inlet almost to the boiling point, i.e., an additional increase in steam production.

A vapor phase begins to form in the process channels, starting from the upper sections of the core and spreading downward. The reactor begins to accelerate. The operating regulator attempts to suppress the power increase, descending and reaching the lower limit switch. An automatic switchover occurs to the backup regulator, which also begins to descend, as recorded by the DREG rapid diagnostic and parameter recording program. However, the efficiency of the four regulator rods is insufficient, and the reactor power continues to slowly increase.

According to the INSAG-7 report (1993):

At 1:09 a.m., the feedwater flow rate was sharply reduced to 90 t/h on the right side and to 180 t/h on the left side, with a total flow rate in the circuit of 56,000–58,000 t/h. As a result, the temperature at the suction [author's note — inlet] of the main circulation pump was 280,8°C (left side) and 283,2°C (right side).

This level—90 tons/hour—is practically zero, within the instrument's margin of error. The water temperature at the reactor inlet has become close to the saturation (boiling) temperature.

However, according to the State Nuclear Academy of Sciences report (1991), “…this was a return of feedwater flow to some average flow rate corresponding to a reactor power of 200 MW and equal to approximately 120 tons/hour on each side of the reactor.” This point of view is shared by a number of specialists.

According to A. G. Tarapon, G. E. Pukhov Institute for Modeling Problems in Power Engineering, National Academy of Sciences of Ukraine (Kiev, Ukraine): "...the capacity was increased only in one (southeastern) quadrant, while in the others it remained at 13,5 MW (residual heat release)..."

At this time, the personnel were placed in extremely difficult conditions. Due to the high steam effect, the power and steam quality, and consequently, the pressure in the steam trap at low power levels, fluctuated up or down due to any disturbances in the multiple circulation circuit. For example, when the BRU-K valves opened, the steam trap pressure dropped, the steam quality briefly increased, and the water level in the steam trap rose. The control unit had to reduce the feedwater flow rate because the water level was +300°C, meaning the turbine was shut down to prevent water from entering the turbine's flow path. Conversely, if the auxiliary main circulating pump was activated, the steam quality dropped, and the water level in the steam trap dropped, requiring an increase in feedwater flow rate, etc. Therefore, the control unit alternately sharply increased and decreased the feedwater flow rate.

THE EIGHTH FATAL ERROR IS A SHARP DECREASE IN FEED WATER CONSUMPTION.

Fall in the OZR level below the permissible level


From 01:12:10 a.m. to 01:18:49 a.m., the DREG program was not running. This was due to the DREG tape being reset by the SDIVT to record the parameters during the "Coast-Down Program..." run.

01:15 am — PN-3,4 are switched on for recirculation (according to the run-down program).
01:18 - TG-8 is synchronized and connected to the network (via the Skala teletype tape),
at 01:18 No.lTG-8 = 32,7 MW (according to the operational log of the NSS at 01:20).
01h 18m 49s - the DREG program is turned on.
01:18:52 AM — 1MPA and 3MPA signals were checked. A 2MPA signal was generated (via the DREG).
01h 18m 54s — AR-2 shutdown due to a malfunction, BRU-K1 TG-8 activation, protection against increasing the level in the BPG to the 2nd limit is disabled; protection against increasing the level in the BTS to the 2nd limit is disabled.
01h 19m 39s — signal “1 PC up”.

01:22:30 — Recording of parameters (before coastdown) on the Skala magnetic tape. According to IAE calculations (performed after the accident), the reactivity margin at this point was ORM = 6–8 st. RR. /According to other data, the ORM margin ranged from 2 to 12 rods with a minimum of 16 RR, which was a gross violation of regulations. The reactor had to be shut down. Additionally, to prevent this from happening, protections were activated to increase the level in the reactor core to the 2nd limit and to increase the level in the reactor coolant system to the 2nd limit./

The operating reactivity margin was significantly lower than normal due to xenon poisoning of the reactor. Out of 211 control rods, according to various estimates, 6–8 were missing; according to Komarov, 1,5 rods; according to V. Fedulenko (I.V. Kurchatov Institute of Atomic Energy), and based on the DREG tapes, only 2 rods (!) were missing, with a minimum of -16.

According to the report (No. 1 INSAG-1), this led to the reactor's emergency protection system (EPS) losing its effectiveness: "Meanwhile, the reactor's reactivity continued to slowly decline. At 1:22:30 a.m., the operator saw on the printout of the rapid reactivity margin assessment program that the operational reactivity margin had reached a value requiring an immediate reactor shutdown. However, this did not stop the personnel, and the tests began... At 1:22:30 a.m., the reactivity margin was only 6-8 rods. This is at least half the maximum permissible margin established by the operating procedure. The reactor was in an unusual, non-scheduled state."

…The work of personnel with an unacceptably small operational reactivity margin led to the fact that almost all the remaining absorber rods were located in the upper part of the active zone.

Under the current conditions, violations committed by personnel led to a significant reduction in the effectiveness of the A3 [emergency protection].”

According to the State Nuclear Regulatory Authority (1991) report, this was a violation of the Regulations, namely: “Operation of a reactor plant with an ORM of 15 RR rods or less during the period… approximately from 01:00 on 26.04.86 until the time of the accident (violation of Chapter 9 of the Regulations)…”

According to the interpretation of INSAG-7, which also testifies to the possibility of xenon poisoning of the reactor: “The consequence of the unsuccessful actions taken to control the reactor was that, in order to compensate for the additional negative reactivity that arose due to xenon poisoning of the core during a power reduction, as well as during the subsequent increase in power to 200 MW, it was necessary to remove some of the operating reserve rods from the reactor, which, according to the Commission, with or without awareness of the severity of the consequences, the personnel transferred the reactor to an unscheduled state, in which the emergency protection ceased to be a guarantee of quenching the nuclear reaction…”.

At 01:22:30 a.m., the SKALA central control system recorded the unit's parameters to magnetic tape. No operational calculations were performed using the PRIZMA program at that time. These were performed after the accident using the magnetic tape removed from the central control system, using the PRIZMA-ANALOG program, outside the Chernobyl Nuclear Power Plant (at the Smolensk Nuclear Power Plant). Control room personnel and SKALA personnel did not have the results of the operational calculations and were unaware of the calculated parameters, including the ORM value, at that time.

Before the accident, the reactor personnel operated the reactor as if blind. They didn't notice the ORM drop below 15 rods due to the length of their calculations. The actual ORM was discovered after the accident, after analyzing Skala's calculations at 1:22 am. SIUR may not have had time to estimate the ORM based on the number of rods inserted (which they can do), as they were very busy operating the reactor at the time. Indeed, it appears they weren't paying attention to the ORM at the time. As the court found, Chernobyl NPP personnel often worked at "limit" levels.

But when they were raising the reactor from the pit, the personnel should have had some understanding of the situation. The rundown was supposed to be carried out by one, the most experienced shift, but by a fateful coincidence, the most inexperienced one was assigned to the job.

According to the State Nuclear Academy of Sciences report (1991), immediately before the tests at 01:22:30: “Under the conditions that arose, a small increase in reactor power (for any reason) due to low subcooling of the coolant to boiling point could lead to an increase in the volumetric steam content in the lower part of the core… Thus, before the start of the tests, the parameters of the core caused an increased susceptibility of the reactor to a self-accelerating process in the lower part of the core… This condition arose not only because there was an increased coolant flow rate than usual…, but primarily due to the low value of the reactor power.”

It should be noted that self-accelerating processes in the reactor are included in the design due to the gigantic positive steam coefficient of 4–5 beta, as well as the absence of a prohibition on operating at low power in the power mode.

While the main circulation pumps (MCPs) were running on coastdown (36,2 s), there were no significant changes. However, after the shutdown of four main circulation pumps (MCPs) powered by the coasting turbogenerator, the positive reactivity created by the reduced water flow in the multiple circulation circuit (MCC) led to an increase in steam quality. The resistance of the fuel channel (FC) increased, and the flow rate through the fuel channel (FC) began to decrease, leading to a further increase in steam quality, and consequently, a rise in reactivity. This triggered an emergency increase in reactor power and the subsequent shutdown of the reactor by the SIUR (Siur-Ion Control System) using the AZ-5 button.

The staff held out hope until the very last moment for the "saving" AZ-5 button; the Chernobyl Nuclear Power Plant often operated "on the brink" in modes with a low ORM margin. Moreover, the reactor's designers insisted that their reactor was safe and that nuclear accidents were completely impossible. I remember those fateful times well. But who could have imagined that it wouldn't work, that the human hand wouldn't be able to keep up with the rapid nuclear processes? As A. Dyatlov, the direct test supervisor, himself admits, the staff was late in pressing the button: "Why Akimov delayed giving the command to shut down the reactor, now it's impossible to find out..."

According to the State Panorama of Russia:

However, it was no longer possible to use the emergency protection system of the reactor of this design under the conditions of the permitted decrease in the ORM, either by emergency signals or manually after the completion of the tests without damage to the core, apparently starting from 00:30 on 26.04.86, which requires verification by additional studies.

How cavitation “finished off” the reactor


Let us also consider the hypothesis of the occurrence of cavitation, which is put forward by specialists from NIKIET.

N. Dollezhal again:

"The uncertainty in the stability of the continuous circulation loop, as well as the fact that one minute before the start of the generator test, the operator sharply reduced the feedwater supply to the separators, apparently caused the occurrence of cavitation."

Cavitation is the formation of cavities (cavitation bubbles, or caverns) in a liquid filled with steam... Moving with the flow... the cavitation bubble collapses, emitting a shock wave and a significant release of energy.

Oh, Yu, Novoselsky:

During reactor startup in the MKU mode, the appearance of nonequilibrium steam at the fuel channel inlets poses no danger: the core is "packed" with absorber rods, and the void effect is negative. In our case, unfortunately, only the reactor's thermal hydraulics resemble MKU mode... After the feedwater supply is almost completely cut off, boiling begins in the upper portion of the fuel channels, and a steam-water mixture with a low steam content (~1%) begins to flow from the core into the separators. After approximately 20 seconds, most of the water volume in the separators is replaced by water at saturation temperature. At this point, testing begins: the safety valve closes, and at 1:23:04, steam supply to the turbine is cut off. The pressure in the circuit begins to increase. Saturated water enters the downcomers from the reactor core, and after 25-30 seconds, cavitation develops in the SAM system due to low superheat. With the appearance of cavitation steam in the lower part of the fuel cell, a powerful positive feedback mechanism is activated: an increase in steam quality causes an increase in energy release, primarily where the steam arrives, i.e., in the lower part of the fuel cell. This, in turn, leads to an increase in steam quality. With an increase in neutron flux density, another positive feedback loop comes into play—accelerated depoisoning of the core. The role of the "end effect" in all of this is poorly understood.

The theory of coolant cavitation in the SAM system is based on experimental data proving that when the coolant temperature at the reactor inlet is close to the boiling point, the coolant boils in the SAM grooves, and the resulting steam enters the reactor fuel channel inlets.

The length of the water communication pipelines from the air defense missile system to the entrances to the technological channels ranges from 5,5 to 24 m; the steam-water mixture travels this distance in one to six seconds and then enters the entrances to the various fuel channels.

Before the explosion: increased vaporization and the void effect


Then, a sharp increase in steam formation in the channels occurs due to the positive steam effect of reactivity, which is associated with the fact that steam, due to its low density, is a poorer neutron absorber than water. This triggers a sharp increase in reactor power due to prompt neutron runaway. This process is accelerated by a powerful positive feedback mechanism: an increase in steam content causes an increase in energy release, which in turn provokes even greater steam production, and so on. Furthermore, the runaway triggers the "burnout" of xenon, which also intensifies the chain reaction. These processes cause the destruction of the fuel channels and a reactor explosion.

A. N. Rumyantsev, one of the experts who warned the designers about the reactor's shortcomings in advance, also identifies this process as the beginning of the accident, since it entailed the introduction of "hot" water into the reactor with a lag of 28 seconds:

The report states that at 1:22 a.m. on April 26, 1986, the operator abruptly reduced the feedwater flow rate, which resulted in an increase in the water temperature at the reactor inlet with a delay equal to the time it took for the water to pass from the separator drums to the reactor… 28-45 seconds. The report states that at 1:23:04 a.m. the shutoff and control valves (SCVs) of turbogenerator #8 were closed and the tests began. By this time, water with an increased temperature had already been supplied to the fuel channels with the longest NVCs for… 19-36 seconds. The reactor continued to operate at a power of 200 MW… in just 36 seconds from the start of the tests, the reactor power, slowly increasing, reached the level that caused the AZ-5 release. …At the time of the AZ-5 release, the TKs in the local supercriticality zone already had an average power level for the zone of 1.2 times the nominal power. Their power continued to increase. Under all the accompanying circumstances, an accident became inevitable.

N. Dollezhal:

At 1:23:04 a.m., the steam supply to the… turbogenerator was cut off [coastdown tests began]. At this time, the emergency protection system should have been activated, but it was disabled; the reactor continued to produce steam for an unknown consumer. Naturally, the pressure in the coolant circuit and the water temperature at the reactor inlet began to rise. In other words, the conditions were precisely those that most likely would lead to the development of powerful hydrodynamic cavitation. At 1:23:40 a.m., i.e., 36 seconds after the second turbogenerator was shut down, the reactor exploded: an accident occurred.

Rumyantsev's calculations reveal the timing of the accident. The second explosion at Unit 4 of the Chernobyl Nuclear Power Plant, which, according to some versions, occurred at 1:23:39 (±1 second), is believed to have occurred. However, the official chronology of events states that the reactor's emergency runaway began at 1:23:43, and the reactor's destruction occurred at 1:23:50–55.

According to INSAG-1 report No. 1, the increase in steam pressure against the background of a sharp drop in the supply of feedwater to the reactor with a decrease in the flow of water through the reactor caused an increase in the reactor power, which, most likely, was the reason for pressing the emergency button.

From the story of witness Lysyuk G.V. (the foreman of the EC), it follows that before Toptunov pressed AZ-5, he managed to shout: “The reactor power is growing at an emergency rate!”

In December 1987, the Swedish Nuclear Power Inspectorate (cited by O. Novoselsky) proposed a similar scenario for the Chernobyl accident: steam bubbles formed during main circulation pump cavitation enter the fuel channels (FCs). Their formation is caused by low water subcooling (i.e., water temperature close to the boiling point) at the pump inlet. Given the high void effect reactivity present in the reactor at the time, this steam triggered a powerful fission flare (reactor runaway). This localized energy surge resulted in the destruction of numerous fuel channels in the lower section. The second explosion was caused by steam displacing water from the upper section of the core. In other words, a large positive void effect again played a role. Over time intervals of several seconds, the sign and magnitude of the equivalent fast reactivity power effect is almost entirely determined by the steam (void) effect. The remaining effects do not have time to make a significant contribution to reactivity.

According to M. Fedulenko (I.V. Kurchatov Institute of Atomic Energy) (in 1986, head of the I.V. Kurchatov Laboratory), steaming the lower and middle sections of the reactor channels did not require a significant increase in power, as the water temperature was practically equal to the saturation (boiling) temperature. This caused the water to be quickly and completely expelled from the reactor channels and replaced by steam, resulting in a rapid, major reactivity spike that triggered a prompt reactor runaway. This runaway "exploded" the fuel assemblies in the lower half of the reactor.

The INSAG-7 final report also effectively acknowledges that core steaming and the void coefficient of reactivity were, at least in part, the cause of the accident:

…Due to the reduced reactor power level at that time, coolant subcooling [the difference between water temperature and its boiling point, in this context water is close to its boiling point] at the core inlet was only insignificant and… could have been zero. These conditions led to the onset of boiling at or near the bottom of the core. Under the operating conditions that existed at that time, the steam coefficient of reactivity was significantly positive, and the core was in a state of increased susceptibility to increased positive steam reactivity feedback in the event of a power increase. Moreover, with the increased coolant flow rate, the margin before cavitation of the circulation pumps decreased.

After the turbine was shut down, the four pumps powered by it began to slow down as the turbine's speed decreased and the voltage of the associated generator dropped. The decreasing flow rate through the core caused an increase in steam quality in the core and triggered the initial positive reactivity feedback, which was, at least in part, responsible for the accident.

They told the truth, hiding it only partially with words.

IXBT Forum on the causes of the accident:

After all, it was precisely this combination: the pit, then 30 minutes of variable load during unscheduled vibration tests (with active boiling, manually adding large quantities of water, and deliberately cranking up the boil-over protection settings), then a rundown with the reactor running—all of this combined to "overturn" the core's neutron field so dramatically that the reactor's runaway, unchecked by the control and safety systems, began. Had any of these unscheduled experiments been removed, the reactor would have shut down, just as it had during the previous rundown attempts in November 85.

The accident at Unit 4 of the Chernobyl Nuclear Power Plant occurred, on the one hand, due to reactor defects and incomplete technical documentation, and on the other hand, due to some incomprehensible pressure exerted on the staff by a department (sector) of the CPSU Central Committee. A second, more important factor was the staff's lack of knowledge about the specifics of the RBMK reactor, their lack of understanding of the thermal-hydraulic and neutronic processes occurring in the multiple circulation circuit (MFCC) and the reactor, and the fact that the unit was manned by the least experienced shift at the time. The staff had problems with risk assessment—they acted with extreme overconfidence, hoping to trigger the life-saving AZ-5 alarm in time.

THE NINTH FATAL ERROR – THE ORM LEVEL FALLING BELOW THE ACCEPTABLE LEVELS. THE REACTOR HAD TO BE SHUT DOWN.

We only have two questions left to answer: what came first—the reactor runaway and, as a result, the pressing of the AZ-5 shutdown button; or was the reactor shut down after all at the conclusion of the experiment, and assess the role of the end effect under conditions where the majority of the control rods had been removed from the core. And second, the accident itself, the description of which is quite extensive. We will attempt to describe these important points in the next note.

The author expresses gratitude to colleagues for their valuable comments made during the writing of the article.

Links:
Gurachevsky V. L. Introduction to Nuclear Energy.
Chernobyl: KOMAROV'S TESTIMONY
Information on the Chernobyl Accident and Its Consequences Prepared for the IAEA, Report No. 1 (INSAG-1)
O. Yu. Novoselsky, Yu. M. Cherkashov, K.P. Checherov, TECHNICAL ASPECTS OF THE ACCIDENT AT UNIT 4 OF THE CHERNOBYL NUCLEAR POWER PLANT
The truth about Chernobyl lies... in Moscow, Sergei YANKOVSKY, Zerkalo Nedeli No. 16 (441) Saturday, April 26 - May 7, 2003
CHERNOBYL COURT
FOURTH BLOCK, Investigators' Version
Grigory Medvedev. Chernobyl notebook, M Izvestia 1989.
Information on the Chernobyl Accident and Its Consequences, Prepared for the IAEA, Report No. 1 (INSAG-1)
Dollezhal N.A. At the origins of the man-made world. Notes of a designer. — 2010
CHERNOBYL ACCIDENT: SUPPLEMENT TO INSAG-1: INSAG-7
A.G. Tarapon, RECONSTRUCTION OF THE CAUSE OF THE ACCIDENT AT THE CHERNOBYL NUCLEAR POWER PLANT AND THE PROCESSES OF DESTRUCTION OF THE REACTOR AND PREMISES OF UNIT IV
Chernobyl: KOMAROV'S TESTIMONY
V.M. Fedulenko, in 1986, Head of the Laboratory of Thermal Calculations of Channel Reactors, Department 33 of the I.V. Kurchatov Institute of Atomic Energy
On the causes and circumstances of the accident at Unit 4 of the Chernobyl Nuclear Power Plant on April 26, 1986, Report of the USSR State Industrial Supervision Commission
The principle of cavitation heating changes the concept of thermal energy production
O.Yu. Novoselsky, leading researcher at the N.A. Dollezhal Research Institute of Power Engineering until November 2014, The Legend of the Emergency Protection System That Exploded a Nuclear Reactor
Novoselsky O.Yu., Continuation of the "Legend"
A.N.Rumyantsev, Chernobyl in 2009
N.V. Karpan, CHERNOBYL: REVENGE OF THE PEACEFUL ATOM, http://www.physiciansofchernobyl.org.ua/rus/books/Karpan.html, chapter 6
Quoted from O. Novoselsky, Nuclear News, December 1987, p. 67-68
V.M. Fedulenko, On the Causes and Development of the Accident at Unit 4 of the Chernobyl Nuclear Power Plant
CHERNOBYL ACCIDENT: SUPPLEMENT TO INSAG-1: INSAG-7
71 comment
Information
Dear reader, to leave comments on the publication, you must sign in.
  1. +9
    25 November 2025 05: 12
    TG, TK, PEN, SIUR... Why couldn't they have included footnotes after the text to avoid trying to decipher these far-from-universal abbreviations? This isn't a website about nuclear power plant operations, after all.
    1. +6
      25 November 2025 08: 23
      Sorry, I got carried away with the TG turbogenerator, the PEN feed pump, the SIUR senior reactor control engineer. But overall, is it clear? The zone was steamed up and the reactor was blown apart.
      1. +8
        25 November 2025 10: 08
        Yes, Alexander. Even I, who worked at the power plant for a decade and a half, have a hard time matching familiar abbreviations with text. And many of them, if I haven't forgotten them, I haven't seen them in a while. I worked in the TAI shop, the thermal automation and measurements shop. Anyway, thanks for the detailed article. Yes, a lot of things came into play: the reactor design, human error, and the alleged pressure from the central control...
        1. +4
          25 November 2025 10: 28
          Dmitry, thank you! I agree there's a lot of specificity here. This technical thread is only for specialists. But overall, I tried to write clearly. If something isn't clear, feel free to skip it. Not everyone here is an engineer or a nuclear scientist, that's a fact.
      2. BAI
        +2
        25 November 2025 12: 50
        The option that PEN - planned operational needs - was not considered?
        There have already been cases in the VO where the same abbreviation has completely different meanings in different departments.
  2. +1
    25 November 2025 05: 38
    Bomb this Kyivenergo to hell, since there are always only idiots there.
  3. -4
    25 November 2025 08: 51
    What is the point of this article?
    To draw the right conclusions, you need to have excellent knowledge in this area and accurate information.
    1. +3
      25 November 2025 09: 14
      To draw the right conclusions, you need to have excellent knowledge in this area and accurate information.
      Well, yes, exactly. O. Yu. Novoselsky, Yu. M. Cherkashov, K. P. Checherov, Dollezhal N. A., Fedulenko, Karpan, Rumyantsev. What do you think they possessed?
    2. +6
      25 November 2025 09: 36
      What is the point of this article?
      The point is to educate and seek the truth, to find answers to questions that the official documents about the accident are silent about.
      What does the average citizen know about this accident, other than what they learned from the Anglo-American TV series "Chernobyl"? Do they know that the cause of the Chernobyl accident is quite controversial, and that although the reactor had flaws, all its systems were operational? The accident occurred as a result of a dubious "coastdown" experiment designed to determine the feasibility of providing emergency power to the NPP equipment using turbine inertia, conducted according to a program not approved by any higher-level organization. And most importantly, with numerous deviations from its provisions, which turned out to be extremely tragic! And all this occurred within the highly regulated Soviet system (and, moreover, within the secretive nuclear energy system).
      Why was the experiment decided to be conducted at the Chernobyl Nuclear Power Plant, which "was the only nuclear power plant where neither the director nor the chief engineer were nuclear specialists..."? Why was the personnel's primary motivation for completing the tests quickly, or more precisely, to see them through to completion, no matter the cost? Why was the personnel not familiarized with the experimental program in advance? Why was the testing assigned to the most inexperienced shift, which was not reinforced by more experienced specialists!? Why were representatives of the nuclear safety department not present during the tests!? Why was it necessary to burden the experiment with another complex program of turbine vibration testing, given that the two experiments were incompatible!? Why was it necessary to disable a significant portion of the automatic reactor protection systems and the emergency cooling system (ECCS)!? What was the need to conduct the experiment on a running reactor, which contradicted the entire previous history of these tests!? Why conduct tests at a low (6% of nominal) 200 MW power, which is not designed for reactor operation, when the program called for 700 MW!? Why didn't the staff stop the experiment after the reactor shut down or after the number of control rods in the zone dropped below the standard? ... and so on. Aren't there just too many oddities to this whole story?
      And finally, the main question: why, despite the fact that alternative research has been conducted that shows the inconsistency of the official version, is it stubbornly not revised?
      1. 0
        25 November 2025 10: 26
        I agree, there are many questions about this accident.
        But it is useless to draw any conclusions now.
        After all, not all of the above-mentioned citizens, despite their knowledge and authority, could tell the truth for various reasons.
        Yes, it was a huge tragedy.
        1. +9
          25 November 2025 10: 32
          Vlad - conclusions must always be drawn. They don't depend on time. Forty years isn't that long in historical terms. I think sooner or later a new investigation will be conducted. And then we'll learn a lot of interesting things. When this whole liberal Perestroika thing ends, since 1985...
          1. 0
            25 November 2025 10: 35
            Let's hope so.
            But remember how many versions there were, how many conclusions there were over the past 40 years, what kind of people voiced them, but they still didn’t come to a consensus.
      2. 0
        25 November 2025 16: 51
        To sum up all the issues in one sentence: the potty played on the swing. And the staff couldn't play in sync with the potty.
        This is a very rough comparison.
        As for the coasting, well, all the station workers experimented with it.
        About the overlap of two experiments in one—socialism and the desire to become a medalist, upon whom a golden rain of professional glory and awards will pour.
        PS to all the indignant readers who don't know the specialized terminology, start with the boring regulations.
      3. +4
        25 November 2025 20: 48
        Quote: Alexander Odintsov
        Why did they decide to conduct the experiment at the Chernobyl Nuclear Power Plant, which “was the only nuclear power plant where neither the director nor the chief engineer were nuclear specialists at all…”?
        I heard they originally wanted to conduct this experiment at the Leningrad Nuclear Power Plant, but the plant's director dug in his heels and told everyone to leave, even though they threatened to expel him from the Party. Maybe that's why?
        1. +4
          25 November 2025 23: 09
          They definitely wanted to go to Kurskaya, but they also sent me away!
      4. +1
        26 November 2025 14: 13
        Quote: Alexander Odintsov
        What is the point of this article?
        Why was the primary motivation for the personnel's behavior the desire to complete the tests quickly, or more precisely, to see them through to completion, no matter what? Why conduct the tests at a low (6% of nominal) 200 MW power, which is not designed for reactor operation, when the program required operation at 700 MW!? Why didn't the personnel stop the experiment either after the reactor shut down or after the number of control rods in the zone fell below the standard? ...and so on?

        Because the next test could only be carried out during the next reactor shutdown for maintenance.
        Dyatlov wrote that there was no prohibition in the instructions to operate at a capacity of 200 MW.
        He also wrote that the calculation of the number of rods was not carried out in real time, but with a delay, and to get a printout, you had to run to the next room, about 20 meters away...
        1. +2
          26 November 2025 14: 26
          They didn't want to wait a year. Now we're summing up the results of this 40-year rush.
          The instructions didn't prohibit it. But they made it clear that this was intermediate power and not operational. As our leading nuclear power plant safety specialist, V. Asmolov, noted:
          It stabilized at 200 megawatts. That is, less than 10 percent... For us in the project, this was an unexplored power level. Because a reactor operates at this power either when it's starting up or when it's shutting down."
          1. -1
            26 November 2025 18: 24
            Quote: Alexander Odintsov
            They didn't want to wait a year. Now we're summing up the results of this 40-year rush.
            The instructions didn't prohibit it. But they made it clear that this was intermediate power and not operational. As our leading nuclear power plant safety specialist, V. Asmolov, noted:
            It stabilized at 200 megawatts. That is, less than 10 percent... For us in the project, this was an unexplored power level. Because a reactor operates at this power either when it's starting up or when it's shutting down."

            Why then didn't leading specialist Asmolov include this in the safety instructions?
            Nobody was planning to work for long at 200 MW.
        2. 0
          9 January 2026 17: 22
          Quote: Panin (Michman)
          Dyatlov wrote that there was no prohibition in the instructions to operate at a capacity of 200 MW.

          There was no outright ban. Because it was a short-term transitional regime. His attempt to hide behind it is laughable to technically literate people. It's precisely for such "characters" that they write "don't dry cats in microwave ovens." Yes, such people exist, but allowing them to work with reactors is already a crime.
      5. +1
        30 November 2025 21: 23
        Isn't there too much weirdness to this whole story?

        I agree that there were too many organizational oddities. I attribute this to the industry's closed nature, the belief that reactors wouldn't explode, and the arrogance typical of the time. Let's leave the conspiracy theories for the conspiracy theorists. hi

        Thanks for the article. As a student at MEPhI, we spent a month investigating the accident, but it all happened way back in 1990, so I don't remember the details.
      6. +2
        11 February 2026 11: 00
        I'm not an expert on atomic bombs or nuclear fission, but I'm "tormented by vague doubts" about the coincidence of the Chernobyl accident, perestroika, prohibition, and Rust's flight... not simultaneously, of course, but the chain of events seems to hint at it.
  4. +4
    25 November 2025 09: 17
    The accident at Unit 4 of the Chernobyl Nuclear Power Plant occurred, on the one hand, due to the reactor's defects and incomplete technical documentation, and on the other hand, due to some incomprehensible pressure exerted on the staff by a department (sector) of the CPSU Central Committee. The second most important factor was the staff's lack of knowledge about the specifics of the RBMK reactor, their lack of understanding of the thermal-hydraulic and neutronic processes occurring in the multiple circulation circuit (MFCC) and the reactor, and the fact that the unit was manned by the least experienced shift at the time. The staff had problems with risk assessment—they acted with extreme overconfidence, hoping to activate the life-saving AZ-5 alarm in time. That's all in a nutshell. The rest depends on the technical level of the readers.
    1. +4
      25 November 2025 11: 13
      "and also because of some incomprehensible pressure exerted on the staff by the department (sector) of the CPSU Central Committee"
      Perhaps this is the main reason? Was what happened at the Chernobyl Nuclear Power Plant an act of sabotage, "ordered" by the Soviet leadership, which by then had set a course for the dismantling of the established system? It certainly sounds like nonsense and conspiracy theories, but if you look at what happened in the country afterwards... Is there any compelling evidence that it wasn't sabotage, that this theory is unfounded?
      1. +4
        25 November 2025 12: 06
        The accident was advantageous for the collapse of the USSR; it contains too many coincidences and oddities. As one researcher of the "sabotage" theory believes:

        "Let's now consider... this theory: we deliberately wanted to cause an accident at the nuclear power plant and planned to time it with the start of perestroika. How to do this... would require powerful engineering and scientific support from nuclear specialists;... such a group of nuclear specialists would have to be located somewhere at a closed Western research center, in the US or Europe, and almost certainly under the auspices of the intelligence services. Our job was to provide this group with up-to-date information and implement—one way or another—their recommendations... I have no doubt that such cooperation was established..."
        As the results of research from the USSR and our own studies were received, the conditions for the action gradually became clearer. The results of the accident at the Leningrad NPP turned out to be very valuable, but it took some effort to put the whole thing on the brakes ...
        The coast-down experiment was in this sense a very convenient tool that made it possible to obtain the necessary indicators. All control data was obtained during the coastdown experiment in 1985.”
        1. -1
          26 November 2025 16: 43
          The accident was advantageous for the collapse of the USSR; it contains too many coincidences and oddities. As one researcher of the "sabotage" theory believes:

          "Let's now consider... this theory: we deliberately wanted to cause an accident at the nuclear power plant and planned to time it with the start of perestroika. How to do this... would require powerful engineering and scientific support from nuclear specialists;... such a group of nuclear specialists would have to be located somewhere at a closed Western research center, in the US or Europe, and almost certainly under the auspices of the intelligence services. Our job was to provide this group with up-to-date information and implement—one way or another—their recommendations... I have no doubt that such cooperation was established..."
          As the results of research from the USSR and our own studies were received, the conditions for the action gradually became clearer. The results of the accident at the Leningrad NPP turned out to be very valuable, but it took some effort to put the whole thing on the brakes ...
          The coast-down experiment was in this sense a very convenient tool that made it possible to obtain the necessary indicators. All control data was obtained during the coastdown experiment in 1985.”

          Look closer, not "at a closed Western research center, in the USA or Europe," but at your own NIKIET. laughing

          MOSSAD recruited Alexandrov and Dollezhal to discredit Soviet nuclear energy and block the construction of an industrial reactor for Saddam. wink

          How do you like this version? laughing

          Gorbachev: Then why did you sign a document that says its production must be stopped? <...> You surprise me. Everyone says this reactor isn't finished, its operation could pose a danger, and here you are defending the esprit de corps.

          Meshkov. I defend the honor of nuclear energy <...>

          Gorbachev: You continue to assert what you've been asserting for 30 years, and this is an echo of the fact that the Sredmash sphere was not under scientific, state, or party control. And during the work of the Government Commission, Mr. Meshkov, I received information that you were acting frivolously and trying to cover up obvious facts.

          Gorbachev. Sidorenko V.A. (Deputy Chairman of the USSR State Atomic Energy Supervision Authority) writes that RBMK will not meet modern international requirements even after reconstruction <...>

          Shasharin G.A. (Deputy Minister of Energy and Electrification of the USSR): The physics of the reactor determined the scale of the accident. People didn't know the reactor could overheat in such a situation. There's no certainty that further modifications will make it completely safe. There are dozens of situations where the same thing could happen as in Chernobyl. This is especially true for the first units of the Leningrad, Kursk, and Chernobyl nuclear power plants. The Ignalina Nuclear Power Plant (NPP) can't operate at its current capacity. They don't have an emergency cooling system. They need to be shut down first. <...> I'm certain of it, it's impossible to build any more RBMK reactors. As for upgrading them, the cost wouldn't be justified. The philosophy of extending NPP service life is far from always justified.

          Gorbachev: What should the Kurchatov Institute of Physics do?

          Aleksandrov: I believe this reactor's acceleration property can be eliminated. We have some ideas for solutions to this problem. This could be accomplished within one or two years.

          Gorbachev: Does this apply to currently operating reactors?

          Aleksandrov: The currently operating reactors can be made safe. I'll bet my head, old as it is, that they can be put in order. I ask that you relieve me of my duties as president of the Academy of Sciences and give me the opportunity to correct my mistake related to the shortcomings of this reactor.
          1. +1
            27 November 2025 09: 13
            Dear Arzt!
            MOSSAD recruited Alexandrov and Dollezhal to discredit Soviet nuclear energy and block the construction of an industrial reactor for Saddam.
            I was working at Nikiet during the accident. I think it's unlikely. I think the connection goes back to the Central Committee of the Communist Party of the Soviet Union, which orchestrated the whole thing through the so-called nuclear energy sector. It's been all over the internet for years now. Dyatlov was simply framed, and he lacked the will to follow common sense. He could have been fired, but the accident wouldn't have happened.
      2. 0
        26 November 2025 09: 35
        Was it Gorbachev? Who called? I wouldn't be surprised!
        1. 0
          26 November 2025 16: 29
          Was it Gorbachev? Who called? I wouldn't be surprised!

          Nobody called. It's a tall tale. It's been dealt with a thousand times. negative
          1. 0
            26 November 2025 16: 52
            Dyatlov clearly pushed the tests and pressured his replacements, despite the emerging signals of an impending disaster. Only an authoritarian tyrant could act like that without external motivation. Therefore, the version involving a call from the Central Committee explains his motivation well.
            1. +1
              26 November 2025 16: 58
              Dyatlov clearly pushed the tests and pressured his replacements, despite the emerging signals of an impending disaster. Only an authoritarian tyrant could act like that without external motivation. Therefore, the version involving a call from the Central Committee explains his motivation well.

              Where did he call him? The station? All the conversations were recorded, no one called.
              1. 0
                26 November 2025 17: 08
                Quote: Arzt
                Where did he call him? The station? All the conversations were recorded, no one called.

                Then we'll have to draw a conclusion about Dyatlov's personal qualities, the underestimation of which led to the disaster. The notorious human factor.
                1. -1
                  26 November 2025 17: 14
                  Then we'll have to draw a conclusion about Dyatlov's personal qualities, the underestimation of which led to the disaster. The notorious human factor.

                  Have you read Dyatlov's book? It begins like this:

                  "On April 26, 1986, at one hour, twenty-three minutes, forty seconds, the shift supervisor of Unit No. 4 of the Chernobyl Nuclear Power Plant, Alexander Akimov, ordered the reactor to be shut down upon completion of the work carried out before the shutdown of the power unit for scheduled repairs. The command was given in a calm working environment, centralized control system does not record any emergency or warning signals about deviation of reactor parameters or service systems.

                  Reactor operator Leonid Toptunov removed the cap from the AZ button, preventing accidental operation by mistake, and pressed it. This signal caused 187 reactor control rods to begin moving downwards into the core. The backlights on the control panel lit up, and the rod position indicator needles began moving. Alexander Akimov, half-turned to the reactor control panel, observed this. He also saw the lights on the automatic control rod imbalance indicators "flicker to the left" (his expression), as expected, indicating a decrease in reactor power. He turned to the safety panel, where he had been monitoring the experiment being conducted.

                  But then something happened that even the wildest imagination couldn't have predicted. After a slight decrease, the reactor's power suddenly began to increase at an ever-increasing rate, and emergency signals appeared. L. Toptunov shouted for an emergency power increase. But he was powerless to do anything. All he could do was hold down the emergency shutdown button, and the control rods were moving into the core. He had no other means at his disposal. And neither did anyone else. A. Akimov shouted sharply, "Shut down the reactor!" He rushed to the control panel and de-energized the electromagnetic clutches driving the control rods. The action was correct, but futile. After all, the control rod logic, that is, all its logical circuit elements, had worked correctly, and the rods were moving into the core. Now it's clear: after pressing the emergency shutdown button, there were no correct actions, no means of rescue. The other logic had failed!

                  With a short interval, two powerful explosions followed. The AZ rods stopped moving, not having completed half the way. They had nowhere else to go.

                  At 1:23:47, the reactor was destroyed by a prompt neutron power surge. This is a meltdown, the ultimate disaster that can happen to a power reactor. It wasn't thought through, there was no preparation for it, and no technical measures for containment were envisaged at the unit or station. There are no organizational measures either."


                  There was no emergency or pressure there. The reactor exploded out of nowhere during a scheduled shutdown. fellow
                  1. +2
                    26 November 2025 19: 14
                    The reactor exploded out of nowhere during a scheduled shutdown.

                    Have you read the article?
                    She's all about how there was no planned shutdown—the reactor was abused for half an hour, with all safety systems disabled. However, Alexandrov said this right away, even before all the commissions' findings.
                    The problem with the design was that there was no protection against this sequence of actions, which is very reminiscent of INTENTIONAL overclocking.
                    Of course, it is possible to create a structurally different reactor (VVER, for example) and the TA sequence will not destroy it, but another one will certainly be found which (if you do not build a layered defense against a fool) will also lead to a catastrophe.
                    It's just that in the Union they didn't really like the rule: all the mistakes that personnel can make, they will make, but they won't stop there and will also make all the mistakes that they can't make.
                    Chernobyl was a very bitter lesson, but we learned it, and I was taught to take it into account in our projects. But then the Soviet Union collapsed, and in most places, safety was completely neglected. am
                    1. -1
                      26 November 2025 19: 49
                      Have you read the article?
                      She's all about how there was no planned shutdown—the reactor was abused for half an hour, with all safety systems disabled. However, Alexandrov said this right away, even before all the commissions' findings.
                      The problem with the design was that there was no protection against this sequence of actions, which is very reminiscent of INTENTIONAL overclocking.
                      Of course, it is possible to create a structurally different reactor (VVER, for example) and the TA sequence will not destroy it, but another one will surely be found which (if you do not build a layered defense against a fool) will also lead to a catastrophe.
                      It's just that in the Union they didn't really like the rule: all the mistakes that personnel can make, they will make, but they won't stop there and will also make all the mistakes that they can't make.
                      Chernobyl was a very bitter lesson, but we learned it, and I was taught to take it into account in projects. But then the Soviet Union collapsed, and in most places, safety was completely ignored.

                      Is increasing/decreasing power rape in your opinion? It's the normal operation of any power system, including a reactor. On nuclear submarines, this is done very intensively. wink

                      And Alexandrov forgot to clarify that he himself orchestrated this program, including the shutdown of the defenses, which, by the way, wasn't initiated by Dyatlov's shift, or even the previous one. But the previous one by the previous one. Yes

                      The acceleration was, of course, intentional; it's one of the reactor's normal operating modes. But who knew that its brakes were designed in such a way that they also accelerate first and then decelerate. laughing
                      1. 0
                        9 January 2026 17: 29
                        Quote: Arzt
                        Have you read the article?
                        She's all about how there was no planned shutdown—the reactor was abused for half an hour, with all safety systems disabled. However, Alexandrov said this right away, even before all the commissions' findings.
                        The problem with the design was that there was no protection against this sequence of actions, which is very reminiscent of INTENTIONAL overclocking.
                        Of course, it is possible to create a structurally different reactor (VVER, for example) and the TA sequence will not destroy it, but another one will surely be found which (if you do not build a layered defense against a fool) will also lead to a catastrophe.
                        It's just that in the Union they didn't really like the rule: all the mistakes that personnel can make, they will make, but they won't stop there and will also make all the mistakes that they can't make.
                        Chernobyl was a very bitter lesson, but we learned it, and I was taught to take it into account in projects. But then the Soviet Union collapsed, and in most places, safety was completely ignored.

                        Is increasing/decreasing power rape in your opinion? It's the normal operation of any power system, including a reactor. On nuclear submarines, this is done very intensively. wink

                        And Alexandrov forgot to clarify that he himself orchestrated this program, including the shutdown of the defenses, which, by the way, wasn't initiated by Dyatlov's shift, or even the previous one. But the previous one by the previous one. Yes

                        The acceleration was, of course, intentional; it's one of the reactor's normal operating modes. But who knew that its brakes were designed in such a way that they also accelerate first and then decelerate. laughing

                        Have you read anything about the Chernobyl disaster other than propaganda? They disabled numerous security systems that would have prevented such an outcome. They were in their way...
                      2. 0
                        9 January 2026 17: 29
                        Quote: Arzt

                        Is increasing/decreasing power rape in your opinion? It's the normal operation of any power system, including a reactor. On nuclear submarines, this is done very intensively.

                        Have you read anything about the Chernobyl disaster other than propaganda? They disabled numerous security systems that would have prevented such an outcome. They were in their way...
  5. +2
    25 November 2025 11: 07
    Why didn't anyone want to say stop?

    Because perestroika was underway and a nuclear accident was vital to its success - like Rust's flight, the ship accident, and so on.
    Now it is completely clear why this happened in the Ukrainian SSR.
  6. 0
    25 November 2025 11: 25
    I once came across a description of how the protection system on the reactors of a Project 941 Akula (NATO codenamed Typhoon) submarine worked. It was said to be able to shut down the reactors even when there was no electricity, even if the submarine was lying on its side.
    1. -1
      26 November 2025 06: 24
      Quote: Bad_gr
      I once came across a description of how the protection system on the reactors of a Project 941 Akula (NATO codenamed Typhoon) submarine worked. It was said to be able to shut down the reactors even when there was no electricity, even if the submarine was lying on its side.

      Yes, perhaps it was possible to lower the compensating grid manually, as was done during the accident that killed Perminov, but how could this have prevented the accident at the Chernobyl Nuclear Power Plant?
      1. +1
        26 November 2025 10: 26
        Quote: Panin (Michman)
        Yes, perhaps it was possible to lower the compensating grid manually, as was done during the accident that killed Perminov, but how could this have prevented the accident at the Chernobyl Nuclear Power Plant?
        My message was purely for information (on the topic of reactor protection) and is not related to the Chernobyl Nuclear Power Plant under discussion.
  7. +3
    25 November 2025 12: 19
    It's reminiscent of the situation with hydrogen peroxide torpedoes in the navy. As long as all regulations and instructions are followed, the torpedo is relatively safe. If regulations are not followed, or if command attempts to substitute regulations with orders, expect disaster.

    In general, the situation evokes only one reaction - palm-face:
    Let's experiment with a guided nuclear bomb near a city of a million people. Last time, there was no boom, and the tail emission missed the city.
    1. -1
      26 November 2025 06: 30
      Quote: Alexey RA
      It's reminiscent of the situation with hydrogen peroxide torpedoes in the navy. As long as all regulations and instructions are followed, the torpedo is relatively safe. If regulations are not followed, or if command attempts to substitute regulations with orders, expect disaster.

      In general, the situation evokes only one reaction - palm-face:
      Let's experiment with a guided nuclear bomb near a city of a million people. Last time, there was no boom, and the tail emission missed the city.

      The reactor's technical requirements should have stated clearly and unambiguously: "The reactor must always be subcritical, and any personnel actions must not lead to unstable operation."
      Everything else is a problem for developers and manufacturers.
      The fact that the RBMs did not meet these requirements is already a problem of reducing the cost of the design for the sake of savings.
      1. +2
        26 November 2025 08: 31
        Quote: Panin (Michman)
        The reactor's technical requirements should have stated clearly and unambiguously: "The reactor must always be subcritical, and any personnel actions must not lead to unstable operation."

        Documentation and instructions can't cover everything if there's a "quirky" individual within the system with initiative, or if someone's ambitions demand results at any cost. The situation developed outside the scheduled work schedule, and the shift's knowledge was insufficient for this situation. Line staff are usually well-prepared for routine situations according to instructions and protocols, but working in emergency situations, when the instructions fail, requires deeper knowledge and an understanding of the physics of the process. They lacked both, plus Dyatlov exerted his "authority." So, they were hoping for a "button."
        Any complex piece of equipment can be ruined by experimentation. For example, I haven't seen any car manuals that say you can't engage first or reverse gear at 100 km/h. I suppose you can, if you really want to...
        1. +1
          26 November 2025 11: 33
          Basically, there's no point in experimenting on line equipment with line personnel, especially near a city. The Leningrad Nuclear Power Plant wasn't enough for them... Build an RBMK reactor somewhere on the Putorana Plateau (or even better, on Novaya Zemlya) – and then you can at least disassemble the core manually.
          Experiments could be carried out with the same success at city water treatment plants.
        2. -1
          28 November 2025 10: 45
          Quote: Cympak
          Quote: Panin (Michman)
          The reactor's technical requirements should have stated clearly and unambiguously: "The reactor must always be subcritical, and any personnel actions must not lead to unstable operation."

          Documentation and instructions can't cover everything if there's a "quirky" individual within the system with initiative, or if someone's ambitions demand results at any cost. The situation developed outside the scheduled work schedule, and the shift's knowledge was insufficient for this situation. Line staff are usually well-prepared for routine situations according to instructions and protocols, but working in emergency situations, when the instructions fail, requires deeper knowledge and an understanding of the physics of the process. They lacked both, plus Dyatlov exerted his "authority." So, they were hoping for a "button."
          Any complex piece of equipment can be ruined by experimentation. For example, I haven't seen any car manuals that say you can't engage first or reverse gear at 100 km/h. I suppose you can, if you really want to...

          Read about Fukushima and how the staff there used flashlights to read the emergency procedures. They couldn't find any and had to improvise.
  8. 0
    25 November 2025 12: 24
    I devoted 2 years of study to this topic.
    1. And most importantly, the RBMK-1000 reactor had critical design flaws. Alexandrov and Dollezhal covered their own asses from punishment, shifting the blame entirely to the personnel. Below is a quote from Alexander Rumyantsev's article and a link to it:
    "It was found that only the second eigenvalue was positive and lay in the range of unity, which was expected for Keff. Following the formal logic of interpreting the eigenvalues ​​and eigenvectors of matrix operators, it could be concluded that initially the most stable state of the reactor core is its “absence”. This was the “first” bell regarding the initial safety of future RBMK reactors. Subsequent analysis of available information on the problems of eigenvalues ​​and eigenvectors of matrix operators showed that this effect is typical for the so-called “loosely coupled systems”, i.e. systems consisting of many subsystems that have weak connections with each other. From calculations and experiments it was known that a group of 35-40 fresh FCs of the RBMK type already forms a critical system. From calculations it followed that in the presence of up to 1700 FCs in the core of an RBMK reactor, even after reaching equilibrium burnup, a local group of 70-110 FCs can also reach criticality if it does not contain a DP or inserted control rods."
    http://accidont.ru/memo/Rumjantsev.html
    The reason they blamed the entire situation on the staff was political. If the design flaw had been revealed, it would have been a fatal blow to the prestige of the USSR and its advanced nuclear energy expertise.
    1. +4
      25 November 2025 14: 17
      Dear Matvey, you're right: the RBMK reactor is a poor design. The State Nuclear Supervision Agency's report largely absolves the staff of blame. But the truth lies in the middle. It's outlined in the conclusion at the end of the article (posted just above). At the same time, the staff was simply let down. The most inexperienced shift was selected. Dyatlov was threatened by the CPSU Central Committee sector, which was harassing the staff. But surely they should have understood that the reactor couldn't be abused like that?
      1. 0
        5 December 2025 11: 16
        Well, I can't agree with the middle part... unfortunately... You indicated Nikolai Karpan's book "Revenge of the Peaceful Atom" as the literature used, I read it in its entirety, as well as A.S. Dyatlov's memoirs "Chernobyl. How it was", as well as the updated IAEA INSAG 7 report. There are many points described there that are recognized as having existed at the reactor, but which were not specified in the reactor operating instructions: the side ionization chambers - the sensors had an error of several percent (2, if I remember correctly) and just a dip of 0.28 minutes to 30 MW, according to the error of the sensors, it could well have been a dip to 0 MW of thermal power, the instructions on this account said to immediately shut down the reactor according to the 5th emergency protection protocol. The shortened absorber rods (USPs) that were supposed to be inserted into the core from below didn't exist; there were only designs developed as part of post-accident improvements to the RBMK-1000 reactors. Karpan's calculations show that the reactor's runaway in the lower right quadrant of the core would not have occurred if these lower USP rods had been in place. And I won't mention the positive steam and fast power coefficients—according to nuclear safety regulations, they should have been negative to prevent the reactor from developing a tendency toward explosive runaway! The grid size for the fuel channels was incorrectly chosen: 250 mm; if it had been 200 mm or 300 mm, the coefficients listed above would have been negative. Not a single instruction mentioned the reactor's extremely unstable operation and its tendency to form localized subcritical zones at low power and high feedwater flow rates, nor the crucial importance of the Operating Reactivity Margin! And, of course, there's our beloved displacer end effect, which became the detonator that triggered the catastrophic runaway process... The graphite tips were immediately cut off after the accident, as they acted as neutron moderators, displacing water—a neutron absorber—from the reactor channel, thereby causing the reactor to run away. And then there were the lower water lines, the longest of which tended to supply a steam-water mixture to the bottom of the reactor that was no longer suitable for normal fuel rod cooling!!! Thus increasing the risk of uncontrolled runaway with a positive void coefficient...
    2. -5
      25 November 2025 15: 21
      I devoted 2 years of study to this topic.
      1. And most importantly, the RBMK-1000 reactor had critical design flaws. Alexandrov and Dollezhal covered their own asses from punishment, shifting the blame entirely to the personnel. Below is a quote from Alexander Rumyantsev's article and a link to it:
      "It was found that only the second eigenvalue was positive and lay in the range of unity, which was expected for Keff. Following the formal logic of interpreting the eigenvalues ​​and eigenvectors of matrix operators, it could be concluded that initially the most stable state of the reactor core is its “absence”. This was the “first” bell regarding the initial safety of future RBMK reactors. Subsequent analysis of available information on the problems of eigenvalues ​​and eigenvectors of matrix operators showed that this effect is typical for the so-called “loosely coupled systems”, i.e. systems consisting of many subsystems that have weak connections with each other. From calculations and experiments it was known that a group of 35-40 fresh FCs of the RBMK type already forms a critical system. From calculations it followed that in the presence of up to 1700 FCs in the core of an RBMK reactor, even after reaching equilibrium burnup, a local group of 70-110 FCs can also reach criticality if it does not contain a DP or inserted control rods."
      http://accidont.ru/memo/Rumjantsev.html
      The reason they blamed the entire situation on the staff was political. If the design flaw had been revealed, it would have been a fatal blow to the prestige of the USSR and its advanced nuclear energy expertise.

      + 100500. There is no point in the atom; the liquidation of the accident cost 3,5 times more than the entire nuclear energy industry of the USSR generated during its entire existence.

      The most astonishing thing is that everyone can see right now, from the SVO, what a bomb this nuclear power plant is. And no conclusions are drawn. stop This is the lobby of Rosatom! laughing angry
      1. 0
        27 November 2025 12: 31
        stop building nuclear power plants)))))....................
        1. -2
          28 November 2025 10: 49
          Quote: Nastia Makarova
          stop building nuclear power plants)))))....................

          Ideally, that's what should be done. All this construction in unstable countries greatly increases the risk of radioactive material proliferation.
          1. +1
            28 November 2025 12: 07
            Actually, we were talking about Russia, the US is building, France is building
      2. +1
        5 December 2025 11: 28
        Please, sir, answer a few questions:
        Do you acknowledge that the Crimean peninsula is an integral part of the Russian Federation, the Russian world, watered with Russian blood and is an object that cannot be transferred to any other party?!
        Do you support the policy of the Supreme Commander-in-Chief of the Russian Armed Forces, Comrade V.V. Putin?!
        Do you believe that the Special Military Operation is a forced response by the collective West to the approach of NATO infrastructure and its nuclear weapons to the borders of the Russian Federation with hostile goals?!
        Isn't TsIPSo asleep? Well, comrade Security Officer isn't eating his bread in vain. Victory will be with Russian arms! Death to the Ukrainian fascist scum and all its Western handlers!
    3. +1
      26 November 2025 08: 49
      I'd like to remind you that this reactor was originally designed not as a power plant, but for plutonium production. It was done in a tight timeframe, in a hurry. Plutonium was desperately needed. And then... Smart minds decided to implement this vessel-less reactor, relatively cheap and powerful, into the electric power industry.
      1. 0
        5 December 2025 11: 40
        Well, the reactor building was there—a biological shield, so to speak. There's no concrete cap like the one over the VVER reactor over the RBMK reactor; it's absolutely monstrous there.
  9. +3
    25 November 2025 16: 53
    And most importantly, the RBMK-1000 reactor had critical design flaws.

    This reactor had completely acceptable and non-critical technical problems characteristic of all technical products throughout the history of technology and in particular of all nuclear reactors.
    These problems were well known from the experience of the Leningrad Nuclear Power Plant; they were known, and recommendations were made on what not to do with that reactor. And exactly what not to do was done at the Chernobyl Nuclear Power Plant. They did it at night, when management wasn't reporting for work, and during tests that could be conducted on a test rig, not on a running reactor.
    The reactor was removed from the iodine pit in violation of the basic principles that a university student should know.
    And finally, the most symbolic thing. The main culprits (including that same Dyatlov) were acquitted at the very beginning of the "democracy" in Russia. Sakharov himself stood up for them. After all this, they want to convince us that this wasn't intentional sabotage, but rather "the reactor is bad," "the Soviet system is bad," and so on and so forth.
    There was no reactor in the world then, nor today, that could not be destroyed by the deliberate efforts of its personnel.
    1. +1
      26 November 2025 06: 37
      Quote: Kostadinov
      And most importantly, the RBMK-1000 reactor had critical design flaws.


      These problems were well known from the experience of the Leningrad Nuclear Power Plant; they were known and recommendations were given on what not to do with this reactor.
      And finally, the most symbolic thing: the main culprits (including that same Dyatlov) were acquitted at the beginning of the "democracy" in Russia. Sakharov himself interceded for them.
      Democrats, they are such democrats.
      The errors may have been known, but no notifications or warnings were sent out. The redesign of the rods and adjustments to the operating instructions were implemented only after the accident.
      1. 0
        26 November 2025 09: 56
        Quote: Panin (Michman)
        The redesign of the rods and adjustments to the operating instructions were introduced only after the accident.

        I wonder if the instructions say anything about not "throwing boots at the control panel" or about prohibiting the use of "democratic Western" TVELs?
        Clearly, the instructions were refined based on experience. But much of what proactive "general managers" might still be able to devise likely hasn't yet been written down. And even if it is, they'll somehow be able to overcome or circumvent all the restrictions and obstacles.
        1. 0
          26 November 2025 16: 08
          Quote: Cympak
          I wonder if the instructions say anything about not "throwing boots at the control panel" or about prohibiting the use of "democratic Western" TVELs?
          Obviously, the instructions were supplemented based on post-experience.

          So... it's a classic: "Do not dry pets in the microwave.". smile
  10. -4
    25 November 2025 23: 37
    Quote: Alexander Odintsov
    What does the average citizen know about this accident, other than what they learned from the Anglo-American TV series "Chernobyl"? Do they know that the cause of the Chernobyl accident is quite controversial, and that although the reactor had flaws, all its systems were operational? The accident occurred as a result of a dubious "coastdown" experiment designed to determine the feasibility of providing emergency power to the NPP equipment using turbine inertia, conducted according to a program not approved by any higher-level organization. And most importantly, with numerous deviations from its provisions, which turned out to be extremely tragic! And all this occurred within the highly regulated Soviet system (and, moreover, within the secretive nuclear energy system).

    So, I, a typical "average citizen," found out. So what? I lack the expertise necessary to evaluate what's written. I think I do, too, as do most readers. Official conclusions have been reached, the culprits have been named. I think it's high time to let this go...
    1. -1
      26 November 2025 10: 13
      Although I have no connection to nuclear energy, I really enjoyed this series of articles about the causes of the Chernobyl accident for its detailed analysis and leisurely analysis of the entire situation, explaining the physical processes occurring in the reactor.
      The "forgive and forget" approach limits the ability to conduct a dispassionate post-mortem analysis without the influence of political considerations and to obtain a more realistic picture of the disaster, which would allow for more accurate conclusions and consideration of possible causes to prevent similar accidents in the future.
      And the list of disasters for which not all the i's have been dotted is quite extensive:
      - the Komsomolets submarine disaster
      - the Kursk submarine disaster
      - the death of the cruiser "Moscow"
      - failure of the beginning of the Second World War
      -
      1. 0
        26 November 2025 16: 24
        Although I have no connection to nuclear energy, I really enjoyed this series of articles about the causes of the Chernobyl accident for its detailed analysis and leisurely analysis of the entire situation, explaining the physical processes occurring in the reactor.
        The "forgive and forget" approach limits the ability to conduct a dispassionate post-mortem analysis without the influence of political considerations and to obtain a more realistic picture of the disaster, which would allow for more accurate conclusions and consideration of possible causes to prevent similar accidents in the future.

        This is a shadow on the fence. laughing In reality, this is a showdown between the reactor's developers (NIKIET) and its operators. Since the operators are all gone now, the developers, just like back then, are trying to push through their version. But even then, despite intense pressure from Alexandrov and other bigwigs, it didn't work.

        The resonance was too powerful, the country practically fell apart because of it, the investigation was tough and relatively objective, it was not possible to blame everything on the ferocious Dyatlov angry and stupid Akimov fool )).

        Essentially, the author of the article is simply rehashing unverified theories about "calls from the Central Committee," "violations" of the Regulations, and so on. All of this has been covered in previous articles. If you're interested, read my comments. I just don't feel like explaining the same thing for the tenth time.
        1. -1
          26 November 2025 16: 39
          Quote: Arzt
          This is just a sham. In reality, this is a showdown between the reactor's developers (NIKIET) and its operators. Since the operators are all gone, the developers, just like back then, are trying to push through their own version of events.

          One might agree with you if it weren't for the fact that identical RBMK-1000 reactors are installed at the Leningrad Nuclear Power Plant, Kursk Nuclear Power Plant, Chernobyl Nuclear Power Plant, and Smolensk Nuclear Power Plant. They are still operating today. If the problem were in the reactor design, these nuclear power plants would have been decommissioned, or they would have suffered similar technical problems.
          The author, in my opinion, has presented a convincing version that the cause of the Chernobyl accident was a difficult-to-predict combination of personnel actions and design flaws in the reactor, which together led to the disaster.
          Quote: Arzt
          In essence, the article's author simply recycles unverified versions of "calls from the Central Committee," "violations" of the Regulations, etc.

          The protocols of Dyatlov's staff and teams' actions have long been published. I read them long ago, and even without those articles, it seemed to me that Dyatlov was doing everything he could to pressure the staff with his authority and was driving the reactor toward disaster for the sake of conducting the tests. And then it turned out that the reactor was to blame for allowing Dyatlov to blow it up...
          1. -1
            26 November 2025 16: 52
            This is just a sham. In reality, this is a showdown between the reactor's developers (NIKIET) and its operators. Since the operators are all gone, the developers, just like back then, are trying to push through their own version of events.

            One might agree with you if it weren't for the fact that identical RBMK-1000 reactors are installed at the Leningrad Nuclear Power Plant, Kursk Nuclear Power Plant, Chernobyl Nuclear Power Plant, and Smolensk Nuclear Power Plant. They are still operating today. If the problem were in the reactor design, these nuclear power plants would have been decommissioned, or they would have suffered similar technical problems.
            The author, in my opinion, has presented a convincing version that the cause of the Chernobyl accident was a difficult-to-predict combination of personnel actions and design flaws in the reactor, which together led to the disaster.
            Quote: Arzt
            In essence, the article's author simply recycles unverified versions of "calls from the Central Committee," "violations" of the Regulations, etc.

            The protocols of Dyatlov's staff and teams' actions have long been published. I read them long ago, and even without those articles, it seemed to me that Dyatlov was doing everything he could to pressure the staff with his authority and was driving the reactor toward disaster for the sake of conducting the tests. And then it turned out that the reactor was to blame for allowing Dyatlov to blow it up...

            Read my comment above, the transcript of the meeting with Gorbachev. In it, Alexandrov asks for his head to be cut off. laughing

            For all other questions, please see the comments to the previous articles. Everything is covered there.
            Nobody rushed it, they reduced the power, increased it... All of this COULD have been done. And they are still doing it. True, they made about a hundred changes to the reactor design. wink
            1. +1
              26 November 2025 17: 03
              Quote: Arzt
              Read my comment above, the transcript of the meeting with Gorbachev. In it, Alexandrov asks for his head to be cut off.

              This is a knowledge post. According to his recollections, even before the disaster, Dyatlov sometimes made remarks about the RBMK being unknowable. After the disaster, they began searching for the causes, analyzed them, and realized there were a dozen other scenarios that could lead to disaster.
              Why weren't these emergency scenarios immediately noticed? Yes, because they weren't so obvious during normal operation, or because those involved were quietly trying to cover up "certain shortcomings." The RMBK design was inferior to water-moderated reactors, but it was cheaper and faster to build. This was the idea behind the RMBK's promotion: "The economy must be economical!" "Acceleration, perestroika!"
              The conclusion is simple: there was no need to conduct experiments on a reactor that was in an unstable state (in a transition state).
  11. 0
    26 November 2025 11: 26
    Quote: Cympak
    I really liked the elaboration of details and the leisurely analysis of the whole situation with an explanation of the physical processes taking place in the reactor.

    Did you really begin to understand all these physical processes? Or did you simply believe the author?
    1. +2
      26 November 2025 12: 12
      I've expanded my knowledge of nuclear energy. Now I have several avenues for further development. For example, before these articles, I knew nothing about reactor "poisoning" and the iodine pit.
  12. 0
    26 November 2025 13: 08
    Quote: Cympak
    I expanded my horizons of knowledge in the field of nuclear energy.

    Well then, great. But I stand by my opinion: the article is overloaded with technical details. However, they don't affect the conclusions about the cause of the accident.
  13. +2
    26 November 2025 18: 05
    Well, here we go again, the Central Committee of the Party is to blame. negative
    However, according to Komarov, an official from the department (or sector) of the Central Committee of the CPSU, may have given instructions A. Dyatlov was ordered to increase power and conduct a mandatory experiment, threatening him with retirement.
    Perhaps he did, perhaps he didn't. Which official? From which department of the CPSU Central Committee? The order could only have come from someone in the Atomic Energy Sector of the Mechanical Engineering Department of the CPSU Central Committee. Vladimir Vasilyevich Maryin was the head of this sector until 1988. In his memoirs, he writes that between two and three in the morning, an employee of his sector, G.A. Kopchinsky, called him and informed him that a serious accident had apparently occurred at the nuclear power plant and that he needed to report to his workplace. This means V.V. Maryin didn't give any orders. So, maybe it was G.A. Kopchinsky who gave the order? No, he didn't either. According to Kopchinsky's memoirs, he was awakened around two in the morning by a call from his old friend, B.Ya. Prushinsky, chief engineer of VPO Soyuzatomenergo, informing him of an explosion at the nuclear power plant.
    In general, the staff of the CPSU Central Committee generally left work at the end of the workday. Unless, of course, they were preparing for a Plenum or a congress.
  14. 0
    26 November 2025 18: 32
    Quote: Cympak
    One might agree with you if it weren't for the fact that identical RBMK-1000 reactors are installed at the Leningrad Nuclear Power Plant, Kursk Nuclear Power Plant, Chernobyl Nuclear Power Plant, and Smolensk Nuclear Power Plant. They are still operating today. If the problem were in the reactor design, these nuclear power plants would have been decommissioned, or they would have suffered similar technical problems.

    From the memoirs of the head of the atomic energy sector of the Department of Heavy Industry and Energy of the Central Committee of the CPSU, Comrade V.V. Maryin
  15. 0
    26 November 2025 19: 26
    The RBMK was designed so that it could be forced into a state that would trigger a prompt-neutron burnout, and even the designers, let alone the operators, had NO idea. That's all. The average citizen doesn't need to know any other truths.

    And even this truth is only understandable to the average citizen, who knows that during atomic fission, there are prompt neutrons and delayed neutrons. The former allowed the creation of atomic bombs, while the latter allows the creation of nuclear reactors. When the power of a nuclear reactor begins to increase due to prompt neutrons, it turns into a bomb. I don't remember if they teach this to schoolchildren in physics classes. Perhaps they don't.