Severnaya Verf Shipyard named the date of launching the frigate Admiral Golovko

32
Severnaya Verf Shipyard named the date of launching the frigate Admiral Golovko

The second serial frigate of project 22350 Admiral Golovko is preparing to launch. The ceremony is scheduled for late April or early May of this year. This was reported by the press service of the "North Shipyard", leading the construction of ships of this project.

According to a press release, the frigate has now been moved to a floating dock; the ship was taken out of the boathouse at the end of March. Outboard work is underway on the ship, the underwater part of the frigate is painted. Launching is scheduled for late April - early May.



Earlier it was reported that the frigate is planned to be launched during the summer of this year.

"Admiral Golovko" is the third ship in the series of frigates of project 22350 and the second serial. Laid down on February 1, 2012, transmission the fleet scheduled for 2021. At present, the head frigate of project 22350 Admiral Gorshkov is serving in the Russian Navy; the first serial Admiral Kasatonov is getting ready for commissioning. The fourth frigate of the series (third serial) "Admiral Isakov" was laid down on November 14, 2013 and is under construction. On April 23, 2019, two frigates of this project, Admiral Amelko and Admiral Chichagov, were laid down at the Northern Shipyard at once.

Note that Admiral Golovko is the first frigate of project 22350 with a fully Russian power plant. The leading and first production frigates of Project 22350 - Admiral Gorshkov and Admiral Kasatonov - are equipped with diesel engines of Russian production, but gas turbine units (GTU) manufactured by the Ukrainian company Zorya-Mashproekt are used as afterburners. At the "Admiral Golovko" installed domestic analogue of the Ukrainian gas turbine. According to open information, the main power plant of frigates of project 22350 is a gas turbine engine with a total capacity of 65 thousand liters. from. and diesel generators with a total capacity of 4 thousand kW.

Recall that the ships of project 22350 have a displacement of 5 thousand tons with a length of 135 m and a width of 16 m. The frigate is able to cover 4500 miles, while developing a speed of up to 29 knots. Autonomy of swimming is 30 days. Crew - from 170 people.

The frigate is armed with: the 130-mm A-192 artillery mount, the Poliment-Redut anti-aircraft missile system; launchers for 16 anti-ship missiles "Onyx" or "Caliber", anti-submarine complex "Package", anti-submarine helicopter Ka-27.
  • "Northern shipyard"
Our news channels

Subscribe and stay up to date with the latest news and the most important events of the day.

32 comments
Information
Dear reader, to leave comments on the publication, you must sign in.
  1. +11
    April 16 2020 14: 30
    Arseny G. Golovko - commander of the Northern Fleet during the Second World War. Outstanding naval commander!
    It is more impressive when ships are named after the heroes of naval commanders than in honor of cities.
    1. -3
      April 16 2020 14: 51
      We have been building the frigate for 9 years. If we shift the deadlines to the right by one year, we can mark the anniversary of the construction.
      1. -2
        April 16 2020 15: 11
        We have been building the frigate for 9 years. If we shift the deadlines to the right by one year, we can mark the anniversary of the construction.


        Maybe you will try it yourself, I’m sure it will work out faster.

        Is it really not clear that there is a big difference between the construction of the next serial ship, even if it is larger in displacement and completely new from the hull to weapons ?!

        All systems are now brought to the right level and work has gone faster.

        What are you whining for?
        1. -3
          April 16 2020 18: 08
          Quote: Ratmir_Ryazan
          All systems are now brought to the right level and work has gone faster.

          What are you whining for?

          Yes, their work is such a whining here, for any reason .. hi
      2. 0
        April 16 2020 17: 28
        spoon again, cons again.
        all minusers - there is no goal to build a fleet faster - there is a goal to create a new defense industry or defense industry.
        USC is a part of financial industrial groups working with the RF Ministry of Defense.
        example-USA, Yapi et al of the golden billion
    2. +4
      April 16 2020 14: 56
      16 missiles are not enough
      1. +2
        April 16 2020 19: 50
        16 missiles are still not enough

        Watching what rockets ...
        16 Zircons is enough. hi
    3. mvg
      -2
      April 16 2020 17: 37
      Outstanding naval commander!

      What outstanding did? Big words again? Mr. Nelson was not standing near, and Yamamoto was crying loudly, operations such as Pearl Harbor, Golovko developed dozens.
  2. -7
    April 16 2020 14: 31
    Never call dates like this, otherwise such a joyful howl rises here if a delay occurs hi
    Better experienced and went on duty in the oceans .. Here is such information should be!
    1. +4
      April 16 2020 14: 43
      Eight years from the bookmark, before launching ... A crime of some sort. After all, not an aircraft carrier all the same.
      1. +9
        April 16 2020 14: 48
        no. Such a long time because of the power plant, or rather because of delays in the supply of gearboxes.
      2. -11
        April 16 2020 15: 11
        Eight years from the bookmark, before launching ... A crime of some sort. After all, not an aircraft carrier all the same.


        Maybe you will try it yourself, I’m sure it will work out faster.

        Is it really not clear that there is a big difference between the construction of the next serial ship, even if it is larger in displacement and completely new from the hull to weapons ?!

        All systems are now brought to the right level and work has gone faster.

        What are you whining for?
        1. +13
          April 16 2020 15: 19
          Take an example:
          "Admiral Kuznetsov".
          46 tons.
          Not serial. Start of construction 1982, commissioning 1991.
          9 years ...
          And the frigate 5000 tons before launching for 8 years, commissioning is unknown ...
          So whining or crime?
          1. +3
            April 16 2020 16: 14
            Compare the industrial and scientific potential of the USSR and the Russian Federation
            as pointless as you can compare the auto giants ZIL and GAZ in the 70s and now.
          2. 0
            April 16 2020 16: 27
            Almost a feat. And I'm serious
          3. +3
            April 16 2020 17: 34
            Take an example:
            "Admiral Kuznetsov".
            46 tons.
            Not serial.


            Directly not serial? And the fact that this 5th TAVKR in the series of the 1143 “Krechet” project does not bother you?

            And a frigate of 5000 tons


            The frigate pr.22350 is not just 5000 displacement, it is practically only ONE of the latest weapons systems !!! And precisely because of the lag in the development of new systems, there was a delay in most of the air defense !!!

            So that you nagging and panic, or just a provocation.
            1. 0
              April 16 2020 17: 54
              Doesn't bother. There are only common index numbers. "Golovko", by the way, is also the third in the series ...
    2. +4
      April 16 2020 15: 24
      Quote: Mastodon
      Never call dates like this, otherwise such a joyful howl rises here if a delay occurs

      so the article says - Launching is scheduled for late March - early April.March passed and the beginning of April ended. while in the article there is also this - The ceremony is scheduled for late April or early May of this year.. in short, again, the journalists mixed everything in a heap, but in fact I look forward to this frigate, since I knew that he will have our gas turbines, if he is accepted quickly enough, then the series will be driven much faster, and these frigates will be the basis of our surface fleet with gradual modernization already laid !!
    3. +1
      April 16 2020 16: 35
      It’s better not to give a date and build 10 years !! Saw cut saw cut
      1. +2
        April 16 2020 17: 36
        Quote: Clever man
        Saw cut saw cut

  3. D16
    +6
    April 16 2020 14: 38
    Here are the brothers from ZoryaMashProekt who will rejoice for us! drinks .
    1. 0
      April 16 2020 15: 13
      While in China there is such a boom - Zorya is feeling normal.


      Each Chinese QC-280 turbine is made on the basis of the Zori kit, upgraded with the UGT25000.

      Plus India, installations for 11356 + 4 Visakhapatnam destroyers.


      The failure that the Nilgiri series - turbines could not cram, the Indians wanted the classics and took the LM2500. This is minus 8-12 sets of afterburner turbines.
      1. -5
        April 16 2020 15: 50
        Quote: donavi49
        While in China there is such a boom - Zorya is feeling normal.

        =======
        "Zarya-Mashproekt" - has long been "on its side" !!!
      2. D16
        +3
        April 16 2020 19: 04
        Each Chinese QC-280 turbine is made on the basis of the Zori kit, upgraded with the UGT25000.

        You underestimate the Chinese:
        "On the basis of the UGT25000 gas turbine of the Nikolaev Scientific and Production Complex of Gas Turbine Engineering" Zorya-Mashproekt ", Chinese gas turbines QC280 were developed, the performance of which was improved in comparison with the UGT25000, including through the use of LM2500 technological solutions, and the operating power was increased to 30000 kW.
        It is reported that the localization of production of QC280 to date has exceeded 95% "(c)
        https://diana-mihailova.livejournal.com/3576273.html
        The Chinese acted in the best Chinese traditions. laughing
        Plus India, installation for 11356

        These turbines were built many years ago, I won’t be surprised if they were paid for even more years ago.
        4 destroyers Visakhapatnam.

        That's all their bread. Well + overhaul of the Soviet heritage and if the Vietnamese in Zelenodolsk that order. May be..lol. But that is not the point. Even my brother told me that Russia would no longer build large ships with gas turbines after the 14th year. I had to get in with him drinks .
        1. 0
          April 16 2020 21: 06
          Well, even in this news, 5% buy. Moreover, they have a wild volume of ~ 20 turbines per year. Yes, other workshops are not involved, but these 5% can feed themselves.

          These turbines were built many years ago, I won’t be surprised if they were paid for even more years ago.


          No. Ready 1 set to the level packed - there in general, the Navy and the USC flashed. Zorya could send ahead of schedule for money to another transfer. But the USC and the Navy did not fuss. As a result, by the time of the regular paid transfer, the law had arrived.

          The rest in varying degrees of readiness (they should have been sent in increments).

          However, India ordered 4 ships - therefore, also loading, 1 full set from scratch, 2 additional collect.
          Construction contract for India frigates of project 11356 is carried out. This was announced by the head of Rosoboronexport Alexander Mikheev at the Defexpo India-2020 arms exhibition in the Indian city of Lucknow.

          The day before, on February 6, the press service of the Federal Service for Military-Technical Cooperation reported that India will receive two frigates of project 11356 in the first half of 2024. Yet two ships will be built at the Indian shipyard Goa Shipyard Limited.
          1. D16
            +1
            April 16 2020 22: 20
            Well, even in this news, 5% buy. Moreover, they have a wild volume of ~ 20 turbines per year. Yes, other workshops are not involved, but these 5% can feed themselves.

            5% of 20 turbines is the price of one turbine per year. And not a power plant, but just one turbine. By the way, it is not known how many of these 5% went to Russia. After all, they buy a lot of things through gaskets at exorbitant prices here. In a word get rich laughing .
            Zorya could send ahead of schedule for money to another transfer. But the USC and the Navy did not fuss.

            Are you kidding? At Dawn, even the security changed immediately. There, the parties decided on the new line immediately.
            The rest in varying degrees of readiness (they should have been sent in increments).

            However, India ordered 4 ships - therefore, also loading, 1 full set from scratch, 2 additional collect.

            Such orders are made on a prepaid basis. Maybe not 100% th, but very large. A 4th frigate definitely them lol
  4. 0
    April 16 2020 14: 40
    the underwater part of the frigate is painted.

    meerk?
    1. +4
      April 16 2020 15: 39
      Quote: novel xnumx
      the underwater part of the frigate is painted.

      meerk?

      It is called "anti-fouling". Poisonous rubbish, paint exclusively in respirators. To prevent shells and algae from settling on the underwater part of the hull. It probably helps for a while, but then everything grows anyway. I saw a floating workshop that returned from the tropics after a 15-month voyage: its underwater part was overgrown with a shell of shells 15 centimeters thick! It’s a pity, I didn’t think of taking a picture.
      1. +3
        April 16 2020 15: 42
        shell shell of a thickness of 15 centimeters!
        CLASS !!!!
  5. +2
    April 16 2020 14: 45
    And this one in a protective mask laughing drinks
  6. 0
    April 16 2020 15: 03
    We will wait for the launch of the fourth and fifth serial frigates "Admiral Amelko" and "Admiral Chichagov". Since the production of gas turbines has already been completed, I hope that it will be no later than three years.
  7. +3
    April 16 2020 15: 41
    "..."Admiral Golovko" is preparing to launch. The ceremony is scheduled for end of April-beginning of May this year. .... "
    "..... Launching is planned for end of March - beginning of April...... "
    "..... Earlier it was reported that the frigate is planned to be launched during the summer of this year. ..... "
    ========
    WHO wrote the article ?! Who should "lather" the neck?
    So WHEN do they plan to launch it? (To the authors): You can sort it out somehow! request

"Right Sector" (banned in Russia), "Ukrainian Insurgent Army" (UPA) (banned in Russia), ISIS (banned in Russia), "Jabhat Fatah al-Sham" formerly "Jabhat al-Nusra" (banned in Russia) , Taliban (banned in Russia), Al-Qaeda (banned in Russia), Anti-Corruption Foundation (banned in Russia), Navalny Headquarters (banned in Russia), Facebook (banned in Russia), Instagram (banned in Russia), Meta (banned in Russia), Misanthropic Division (banned in Russia), Azov (banned in Russia), Muslim Brotherhood (banned in Russia), Aum Shinrikyo (banned in Russia), AUE (banned in Russia), UNA-UNSO (banned in Russia), Mejlis of the Crimean Tatar People (banned in Russia), Legion “Freedom of Russia” (armed formation, recognized as terrorist in the Russian Federation and banned)

“Non-profit organizations, unregistered public associations or individuals performing the functions of a foreign agent,” as well as media outlets performing the functions of a foreign agent: “Medusa”; "Voice of America"; "Realities"; "Present time"; "Radio Freedom"; Ponomarev; Savitskaya; Markelov; Kamalyagin; Apakhonchich; Makarevich; Dud; Gordon; Zhdanov; Medvedev; Fedorov; "Owl"; "Alliance of Doctors"; "RKK" "Levada Center"; "Memorial"; "Voice"; "Person and law"; "Rain"; "Mediazone"; "Deutsche Welle"; QMS "Caucasian Knot"; "Insider"; "New Newspaper"